TSP/TSP Name:  1939164-TENNESSEE GAS PIPELINE Critical: Y
Notice Type Desc (1):  PIPELINE CONDITIONS Notice Type Desc (2):  CURRENT PIPELINE CONDITIONS
Notice Eff Date/Time:  09/13/2021 2:10:20PM Notice End Date/Time:  12/31/2049 9:00:00AM
Post Date:  9/13/2021 2:10:20 PM Notice ID: 380269
Reqrd Rsp:  1 Notice Stat Desc:  INITIATE Prior Notice: 
Subject:  RESTRICTIONS FOR 09-14-2021 TIMELY CYCLE
Notice Text:

Effective Timely Cycle (9:00) for the gas day of September 14, 2021 Tennessee restricted the following:

OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS

OFO DAILY CRITICAL DAY 1 FOR ALL AREAS SOUTH OF STA 9 FOR OVER-TAKES OUT OF THE SYSTEM AND UNDER-DELIVERIES INTO THE SYSTEM FOR ALL BALANCING PARTIES and OFO MONTHLY CRITICAL DAY 1 FOR ALL OF ZONE 4 FOR OVER-DELIVERIES INTO THE SYSTEM FOR LMPA AND SA BALANCING PARTIES

RESTRICTIONS

·         STA 1 (Segment 101 BH) - through 100% of SOP  due to nominations in excess of operational capacity; 29,303 Dths

·         STA 834 (Segment 834 BH) - through approx 37% of SOP  due to nominations in excess of operational capacity; 71,809 Dths

·         STA 860 (Segment 860 BH) - through approx 17% of SOP  due to nominations in excess of operational capacity; 20,000 Dths

·         MLV 548 (Segment 542 BH) - through 100% of SOP  due emergent repair at STA 542; 2,625 Dths

·         STA 114 East (Segment 114 BH) - through 100% of SIPps  due to scheduled maintenance and nominations in excess of operational capacity; 659 Dths

·         MLV 217 (Segment 217 BH) - through 100% of SOP  due to operational concerns; 20,452 Dths

·         MLV 314 East (Segment 314 BH) - through approx 99% of SOP  due to nominations in excess of operational capacity; 121,372 Dths

·         STA 315 (Segment 315 BH) - through approx 83% of SOP  due to nominations in excess of operational capacity; 253,186 Dths

·         STA 321 (Segment 321 FH) - through approx 38% of SOP  due to nominations in excess of operational capacity; 292,674 Dths

·         Agt/TGP Mahwah New Jersey Bergen Delivery Meter (Pin 420207) - through approx 67% of SIPss  due to nominations in excess of operational capacity; 172,973 Dths

·         MLV 336 East (Segment 336 FH) - through approx 2% of SOP  due to nominations in excess of operational capacity; 907 Dths

·         MLV 355 (Segment 355 BH) - through 100% of SOP  due to operational concerns; 921 Dths

·         STA 237 West (Segment 233 FH) - through 100% of SA  due to force majeure; 19,412 Dths

·         Z5HC North (Segment 299 FH) - through approx 65% of SOP  due to nominations in excess of operational capacity; 393,767 Dths

·         STA 245 (Segment 245 FH) - through approx 74% of SOP  due to scheduled maintenance and nominations in excess of operational capacity; 436,909 Dths

·         MLV 273 (Segment 284 FH) - through approx 96% of SOP  due to nominations in excess of operational capacity; 269,124 Dths

LINEPACK RESTRICTIONS

Payback nominations FROM the pipe in all areas South of STA 9 as well as Payback nominations TO the pipe in Zone 4 will be evaluated at each cycle and scheduled only if operationally feasible. 

STORAGE RESTRICTIONS

No transfers from accounts at TGP Bear Creek Storage to SNG Bear Creek Storage (460017)(IS-PA, FS-PA) until further notice.  Transfers into TGP Bear Creek Storage (460017) from SNG Bear Creek Storage will be allowed under the (IS-PA, FS-PA) storage services with partner approvals.

 

**PLEASE NOTE THAT FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.

**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED SERVICE OUTAGES.

If you have any questions, please contact your Scheduler.