Effective Intraday 2 Cycle (18:00) for the gas day of September 09, 2021 Tennessee restricted the following:
OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS
OFO DAILY CRITICAL DAY 1 FOR ALL AREAS SOUTH OF STA 9 FOR OVER-TAKES OUT OF THE SYSTEM AND UNDER-DELIVERIES INTO THE SYSTEM FOR ALL BALANCING PARTIES and OFO MONTHLY CRITICAL DAY 1 FOR ALL OF ZONE 4 FOR OVER-DELIVERIES INTO THE SYSTEM FOR LMPA AND SA BALANCING PARTIES
RESTRICTIONS
· STA 823 (Segment 823 BH) - through approx 58% of SOP increases due to nominations in excess of operational capacity; 18,963 Dths
· STA 834 (Segment 834 BH) - through 100% of SOP increases due to nominations in excess of operational capacity; 61,881 Dths
· STA 204 (Segment 204 BH) - through 100% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 10,000 Dths
· STA 307 (Segment 307 BH) - through 100% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 14,705 Dths
· MLV 314 East (Segment 314 BH) - through approx 96% of SOP increases due to nominations in excess of operational capacity; 25,214 Dths
· STA 315 (Segment 315 BH) - through approx 69% of SOP increases due to nominations in excess of operational capacity; 38,666 Dths
· STA 321 (Segment 321 FH) - through 100% of SOP increases due to nominations in excess of operational capacity; 76,806 Dths
· MLV 230 (Segment 230 BH) - through 100% of SOP increases due to force majeure; 110 Dths
· Z5HC North (Segment 299 FH) - through approx 82% of SOP increases due to nominations in excess of operational capacity; 78,670 Dths
· STA 245 (Segment 245 FH) - through approx 53% of SOP increases due to nominations in excess of operational capacity; 137,858 Dths
· MLV 273 (Segment 284 FH) - through 100% of SOP increases due to nominations in excess of operational capacity; 5,410 Dths
LINEPACK RESTRICTIONS
Payback nominations FROM the pipe in all areas South of STA 9 as well as Payback nominations TO the pipe in Zone 4 will be evaluated at each cycle and scheduled only if operationally feasible.
STORAGE RESTRICTIONS
No transfers from accounts at TGP Bear Creek Storage to SNG Bear Creek Storage (460017)(IS-PA, FS-PA) until further notice. Transfers into TGP Bear Creek Storage (460017) from SNG Bear Creek Storage will be allowed under the (IS-PA, FS-PA) storage services with partner approvals.
**PLEASE NOTE THAT FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.
**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED SERVICE OUTAGES.
If you have any questions, please contact your Scheduler.