Effective Timely Cycle (9:00) for the gas day of September 10, 2021 Tennessee restricted the following:
OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS
OFO DAILY CRITICAL DAY 1 FOR ALL AREAS SOUTH OF STA 9 FOR OVER-TAKES OUT OF THE SYSTEM AND UNDER-DELIVERIES INTO THE SYSTEM FOR ALL BALANCING PARTIES and OFO MONTHLY CRITICAL DAY 1 FOR ALL OF ZONE 4 FOR OVER-DELIVERIES INTO THE SYSTEM FOR LMPA AND SA BALANCING PARTIES
RESTRICTIONS
· STA 1 (Segment 101 BH) - through 100% of SOP due to nominations in excess of operational capacity; 29,303 Dths
· STA 40 Kn Line (Segment 501 FH) - through approx 97% of SOP due to scheduled maintenance and nominations in excess of operational capacity; 19,073 Dths
· STA 823 (Segment 823 BH) - through approx 95% of SOP due to nominations in excess of operational capacity; 38,610 Dths
· STA 834 (Segment 834 BH) - through approx 66% of SOP due to nominations in excess of operational capacity; 111,295 Dths
· MLV 548 (Segment 542 BH) - through 100% of SOP due to scheduled maintenance and nominations in excess of operational capacity; 13,600 Dths
· MLV 217 (Segment 217 BH) - through 100% of SOP due to operational concerns; 21,866 Dths
· STA 307 (Segment 307 BH) - through 100% of SOP due to scheduled maintenance and nominations in excess of operational capacity; 14,705 Dths
· MLV 314 East (Segment 314 BH) - through approx 98% of SOP due to nominations in excess of operational capacity; 142,321 Dths
· STA 315 (Segment 315 BH) - through approx 84% of SOP due to nominations in excess of operational capacity; 266,325 Dths
· STA 321 (Segment 321 FH) - through approx 40% of SOP due to nominations in excess of operational capacity; 320,580 Dths
· Agt/TGP Mahwah New Jersey Bergen Delivery Meter (Pin 420207) - through approx 22% of SIPss due to nominations in excess of operational capacity; 105,331 Dths
· MLV 336 East (Segment 336 FH) - through approx 6% of SOP due to nominations in excess of operational capacity; 3,012 Dths
· MLV 355 (Segment 355 BH) - through 100% of SOP due to operational concerns; 989 Dths
· STA 237 West (Segment 233 FH) - through 100% of IT due to force majeure; 86,327 Dths
· Z5HC North (Segment 299 FH) - through approx 64% of SOP due to nominations in excess of operational capacity; 420,910 Dths
· STA 245 (Segment 245 FH) - through approx 65% of SOP due to nominations in excess of operational capacity; 381,014 Dths
· MLV 273 (Segment 284 FH) - through approx 90% of SOP due to nominations in excess of operational capacity; 226,543 Dths
· Calpine/TGP Granite Ridge Rockingha Delivery Meter (Pin 420931) - through approx 25% of SOP due to nominations in excess of operational capacity; 52,219 Dths
LINEPACK RESTRICTIONS
Payback nominations FROM the pipe in all areas South of STA 9 as well as Payback nominations TO the pipe in Zone 4 will be evaluated at each cycle and scheduled only if operationally feasible.
STORAGE RESTRICTIONS
No transfers from accounts at TGP Bear Creek Storage to SNG Bear Creek Storage (460017)(IS-PA, FS-PA) until further notice. Transfers into TGP Bear Creek Storage (460017) from SNG Bear Creek Storage will be allowed under the (IS-PA, FS-PA) storage services with partner approvals.
**PLEASE NOTE THAT FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.
**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED SERVICE OUTAGES.
If you have any questions, please contact your Scheduler.