STA 1 Building Protection System Upgrade – *PROJECT UPDATE #1
--10/26/20 through 10/28/20: This project required a station outage which limited volumes flowing north through the station to approximately 275,000 Dths through STA 1 (Segment 101 FH). This work is anticipated to be finished on schedule on October 28, 2020. However, the limitation for south to north throughput of 275,000 Dths at STA 1 (Segment 101 FH) will continue until the work is completed on the Donna Lateral estimated to be on October 30, 2020. Based on customer nominations, potential In the Path restrictions through Segment 101 FH may be at risk.
Due to the anticipated completion of the work at STA 1, effective Timely Cycle for the gas day of Thursday, October 29, 2020, delivery volumes to the Enterprise Agua Dulce Meter (Pin 411306) will be accepted up to meter capacity.
Please let your Scheduler or Account Representative know if you have any questions.