REVISED
Effective Timely Cycle (9:00) for the gas day of June 13, 2019 Tennessee restricted the following:
OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS
MONTHLY CRITICAL DAY 1 OFO FOR ZONE 4 FOR ALL LMSPA AND SA BALANCING PARTIES FOR OVER-DELIVERIES INTO THE SYSTEM
RESTRICTIONS
· Pemex Lateral (Segment 492 FH) - through approx 71% of SOP due to nominations in excess of operational capacity; 1,741 Dths
· MLV 3 (Segment 101 BH) - through approx 58% of SOP due to nominations in excess of operational capacity; 2,065 Dths
· Trnsco/TGP Kinder La Exch (Bi 1 Delivery Meter (Pin 420373) - through approx 38% of SOP due to imbalance management quantity exceeded; 89,383 Dths
· STA 834 (Segment 834 BH) - through approx 66% of SOP due to nominations in excess of operational capacity; 89,627 Dths
· STA 860 (Segment 860 BH) - through approx 78% of SOP due to scheduled maintenance and nominations in excess of operational capacity; 134,038 Dths
· Trnsco/TGP Heidelberg Delivery Meter (Pin 420291) - through approx 22% of SOP due to nominations in excess of operational capacity; 3,091 Dths
· MLV 548 (Segment 542 BH) - through 100% of SOP due to scheduled maintenance and nominations in excess of operational capacity; 13,599 Dths
· STA 204 (Segment 204 BH) - through approx 83% of SOP due to scheduled maintenance and nominations in excess of operational capacity; 29,630 Dths
· STA 307 (Segment 307 BH) - through 100% of SOP due to scheduled maintenance and nominations in excess of operational capacity; 1,100 Dths
· MLV 314 East (Segment 314 BH) - through 100% of SOP due to nominations in excess of operational capacity; 269,328 Dths
· STA 315 (Segment 315 BH) - through 100% of SOP due to scheduled maintenance and nominations in excess of operational capacity; 357,259 Dths
· STA 321 (Segment 321 FH) - through approx 5% of SOP due to scheduled maintenance and nominations in excess of operational capacity; 19,824 Dths
· STA 325 (Segment 324 FH) - through 100% of SOP due to scheduled maintenance and nominations in excess of operational capacity; 200,528 Dths
· Agt/TGP Mahwah New Jersey Bergen Delivery Meter (Pin 420207) - through 100% of SIPps due to pipeline maintenance at delivery location; 272,233 Dths
· Trnsco/TGP Rivervale New Jersey Bergen Delivery Meter (Pin 420101) - through 100% of SIPss due to nominations in excess of operational capacity; 110,735 Dths
· STA 224 (Segment 224 FH) / HC Zn 5 (Segment 299 FH) - through approx 40% of SOP due to scheduled maintenance and nominations in excess of operational capacity; 295,266 Dths
· STA 245 (Segment 245 FH) - through approx 79% of SOP due to scheduled maintenance and nominations in excess of operational capacity; 420,428 Dths
LINEPACK RESTRICTIONS
None
STORAGE RESTRICTIONS
No Interruptible Storage Injection Services (IS-PA) at Bear Creek (460017) or Portland PA (460020).
No transfers from TGP Bear Creek Storage to SNG Bear Creek Storage (IS-PA, FS-PA).
Transfers into TGP Bear Creek from SNG Bear Creek will be allowed under the FS-PA Storage Service ONLY with partner approvals.
**PLEASE NOTE THAT FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.
**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED SERVICE OUTAGES.
If you have any questions, please contact your Scheduler.