Project Update
"Sta 409A: Station Outage
--Project Complete: This project will require a station outage, which will limit throughput through the station and result in restrictions based on customer nominations. The meter listed below will likely experience fluctuations in flow and/or pressures during this time. Potential In the Path nominations may be at risk.
450261 CENEGAS/TGP PEMEX DELIVERY
***Date Change, Previously scheduled for 4/1/19 through 4/21/19.
………………………………"
"Sta 409A: Annual ESD test
-- Project Complete: This project will require a station outage, which will limit throughput through the station and result in restrictions based on customer nominations. Potential in the path restrictions may be at risk.
***Date Change, Previously scheduled for 4/1/19 through 4/14/19.
If you have any questions, please contact your Scheduler.