Notice Detail
           
Return To Results
TSP/TSP Name:  1939164-TENNESSEE GAS PIPELINE Critical: Y
Notice Type Desc (1):  PIPELINE CONDITIONS Notice Type Desc (2):  CURRENT PIPELINE CONDITIONS
Notice Eff Date/Time:  02/10/2019 7:09:19PM Notice End Date/Time:  03/12/2019 9:00:00am
Post Date/Time:  2/10/2019 7:09:19 PM Notice ID: 370445
Reqrd Rsp:  1 Rsp Date:  02/10/2019
Notice Stat Desc:  INITIATE Prior Notice: 
Subject:  RESTRICTIONS FOR 02-11-19 EC
Notice Text:

Effective Evening Cycle (9:00) for the gas day of February 11, 2019 Tennessee restricted the following:

 

OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS

OFO Daily Critical Day 1 for all areas East of STA 254 on the 200 Line only for all Balancing Parties for over-takes from the system and under-deliveries into the system

 

RESTRICTIONS

STA 409A Pemex Lateral (Segment 492 FH) - through approx 77% of SOP EC increases due to nominations in excess of operational capacity; 13,098 Dths

 

STA 1 (Segment 101 BH) – through 100% of SOP EC increases due to nominations in excess of operational capacity; 1,881 Dths

 

STA 224(Segment 224 FH) / HC Zn 5 (Segment 299 FH) – through approx 99% of SOP EC increases due to nominations in excess of operational capacity; 448,880 Dths

 

STA 245 (Segment 245 FH) – through 100% of SOP EC increases due to nominations in excess of operational capacity; 297,268 Dths

 

Wright Receipt Meter (Pin 412181) – through approx 25% of SOP EC increases due to nominations in excess of operational capacity; 11,149 Dths

 

STA 261 (Segment 261 FH Discharge) – through approx 99% of SOP EC increases due to nominations in excess of operational capacity; 142,170 Dths

 

Mendon Delivery Meter (Pin 420285) – through 100% of SOP EC receipt increases due to displacement gas unavailable for backhaul; 2,023 Dths

 

MLV 273 (Segment 284 FH) – through approx 95% of SOP EC increases due to nominations in excess of operational capacity; 137,991 Dths

 

MLV 314 (Segment 314 BH) – through approx 50% of SOP EC increases due to nominations in excess of operational capacity; 49,850 Dths

 

STA 321 (Segment 321 FH) – through approx 75% of SOP EC increases due to nominations in excess of operational capacity; 218,355 Dths

 

STA 325 (Segment 324 FH) – through approx 27% of SOP EC increases due to nominations in excess of operational capacity; 21,082 Dths

 

Mahwah Delivery Meter (Pin 420207) – through approx 41% of SOP EC increases due to nominations in excess of operational capacity; 15,663 Dths

 

MLV 336 (Segment 336 FH) – through 100% of SOP EC increases due to nominations in excess of operational capacity; 764 Dths

 

LINEPACK RESTRICTIONS

No park withdrawals or loans under rate schedule PAL will be allowed utilizing the PAL-D or PAL-AO services system wide until further notice

DS of STA 237 – no payback or lower services OFF the system

STORAGE RESTRICTIONS

No Authorized Overrun Storage Withdrawals (FSMA-AO, FSPA-AO) accepted from Northern (460018), Portland Storage MA (460025), Portland Storage PA (460020) or Bear Creek Storage (460017)

No Interruptible Storage Withdrawals (ISMA, ISPA) accepted from Northern (460018), Portland Storage MA (460025), Portland Storage PA (460020) or Bear Creek Storage (460017)

No transfers from TGP Bear Creek Storage to SNG Bear Creek Storage (IS-PA, FS-PA)

Transfers into TGP Bear Creek from SNG Bear Creek will be allowed with partner approvals

Customers who elected swing on storage (SSO) or storage swing options (SSO) may swing up to their Maximum Daily Withdrawal Quantity (MDWQ) only

 

**PLEASE NOTE THAT FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.

 

**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND

ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED

SERVICE OUTAGES.

 

If you have any questions, please contact your Scheduler.

 

...