TSP/TSP Name:  1939164-TENNESSEE GAS PIPELINE Critical: Y
Notice Type Desc (1):  PIPELINE CONDITIONS Notice Type Desc (2):  CURRENT PIPELINE CONDITIONS
Notice Eff Date/Time:  03/20/2017 3:24:38PM Notice End Date/Time:  04/19/2017 9:00:00am
Post Date/Time:  3/20/2017 3:24:38 PM Notice ID: 362693
Reqrd Rsp:  1 Rsp Date:  03/20/2017
Notice Stat Desc:  INITIATE Prior Notice: 
Subject:  RESTRICTIONS FOR 3-20-17 ID2
Notice Text:
Effective Timely Cycle (9:00) for the gas day of February 9, 2014

Effective Intraday Cycle 2 (18:00) for the gas day of March 20, 2017 Tennessee restricted the following:

 

OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS

OFO Monthly Action Alert for Zone 4 for under-deliveries for LMSPAs

Imbalance Warning for Zones 4, 5 and 6 for under-deliveries and over-takes

 

RESTRICTIONS

STA 1 (Segment 409 BH) – through 100% of IT ID2 increases due to nominations in excess of operational capacity; 30 Dths

 

STA 224 (Segment 224 FH) / HC Zn 5 (Segment 299 FH) – through approx 30% of SOP ID2 increases due to nominations in excess of operational capacity; 22,582 Dths

 

STA 237 (Segment 237 FH) – through approx 36% of SOP ID2 increases due to nominations in excess of operational capacity; 9,813 Dths

 

STA 245 (Segment 245 FH) – through approx 93% of SOP ID2 increases due to nominations in excess of operational capacity; 378,153 Dths

 

STA 307 (Segment 307 BH) – through 100% of IT ID2 increases due to nominations in excess of operational capacity; 55,623 Dths

 

MLV 314 (Segment 314 BH) – through 100% of SOP ID2 increases due to nominations in excess of operational capacity; 51,361 Dths

 

STA 315 (Segment 315 BH) – through approx 96% of SOP ID2 increases due to nominations in excess of operational capacity; 137,488 Dths

 

MLV 336 (Segment 336 FH) – through 100% of SOP ID2 increases due to nominations in excess of operational capacity; 5,021 Dths

 

LINEPACK RESTRICTIONS

Downstream of STA 237 on the 200 Line – through 100% of payback from TGP; 20,000 Dths

 

STORAGE RESTRICTIONS

No transfers from TGP Bear Creek Storage to SNG Bear Creek Storage (460017) (IS-PA, FS-PA)

Transfers into TGP Bear Creek from SNG Bear Creek will be allowed with partner approvals

No transfers from accounts at TGP Northern Storage (IS-MA, FS-MA) to Dominion Harrison Storage (460004) 

Only primary transportation deliveries to the Dominion Harrison Storage Delivery Meter (460004) will be accepted

 

**PLEASE NOTE THAT FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR

CONFIRMATION REDUCTIONS.

 

**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND

ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED

SERVICE OUTAGES.

 

If you have any questions, please contact your Scheduler.

....