TransColorado Gas Transmission Company LLC
September 30, 2026
Force Majeure – TC Segment 310 Blanco Compressor
TransColorado Gas Transmission Company LLC (“TC”) has experienced a mechanical issue described as a jacket water coupling failure, which requires immediate attention. Therefore, the TC Blanco Unit #2 is currently unavailable due to the need for necessary repairs. Accordingly, the operational capacity through Segment 310_BLANCO_COMPRESSOR_BH TD2 constraint will be reduced from 260,000 dekatherms per day (Dth/d) to 180,000 dekatherms per day (Dth/d) effective September 30, 2026, Cycle 5 - Intraday 3, until further notice.
TC will be posting an updated maintenance notice to reflect the total impact through Segment 310_BLANCO_COMPRESSOR_BH TD2 constraint.
TC will provide updates as more information becomes available.
This incident constitutes an event of Force Majeure under TC's FERC Gas Tariff, General Terms and Conditions, Section 14.
For scheduling questions, please call your scheduling representative at (800) 238-3764.
For operational and capacity information, please call Michael Burleson at (719) 640-1577, Hayden Garfield at (719) 726-5311, or Matt Houtz at (719) 726-5230.
For media inquiries, please contact media relations at media_relations@kindermorgan.com
Scheduling questions or concerns
Pipeline Scheduling Hotline (800) 238-3764 option 2,
email CIGSched, or message KMRockiesSched on ICE Chat
Operational issues or concerns
Mike Burleson at (719) 640-1577
Hayden Garfield at (719) 726-5311
Matt Houtz at (719) 726-5230
Marketing questions
Contact your Marketing Representative.
Rich Aten, Manager – Pipeline Scheduling
Transportation and Storage Services
Kinder Morgan Rockies Pipelines
(719) 667-7527 or (719) 648-5253
richard_aten@kindermorgan.com | ICE Chat: raten
Your session will expire in . Click OK to renew your session.