TransColorado Pipeline Company Operations Planning Report for JULY 2024 Issued June 18, 2024
Reissued July 30, 2024
Deletion:
OLATHE C.S. TO RED VALE C.S. (Segment 230): TransColorado cancels the pigging operations Racoon Hollow to Olathe Compressor Station July 31.
2
OLATHE C.S. TO RED VALE C.S. (Segment 230): TransColorado will be performing pigging operations Racoon Hollow to Olathe Compressor Station July 12 and July 31. This outage results in the following impacts.
Dates
Segment
Operating Capacity (MDth/d)
Reduced to Capacity (MDth/d)
TD2 Northbound
July 12
230
260
0
July 31
TD1 Southbound
364
170
JULY 2024
1
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
TRANSCOLORADO GAS PIPELINE COMPANY MAINTENANCE
DOLORES C.S. TO MANCOS C.S. (Segment 250): Mancos Compressor Station, TransColorado, will be performing Station DOT/ESD test July 9 through July 10. This outage results in the following impacts.
July 9
250
220
July 10
238
361
311
334
BLANCO COMPRESSOR (Segment 310): Blanco Compressor Station, TransColorado, will be performing Station DOT/ESD test July 23. This outage results in the following impacts.
July 23 Cycles 1 thru 4
310
178
July 23 Cycle 5
215**
** The nomination limit for this cycle has been prorated for the remaining time in the gas day
BLANCO COMPRESSOR (Segment 310): Blanco Compressor Station, TransColorado, will be performing unit repair July 9 through July 11. This outage results in the following impact.
July 9 thru July 11
Any comments or questions about this report should be directed to Vic Villalva at (719) 520-4251 or Cheryl Bauer at (719) 520-4423.