TransColorado Pipeline Company Operations Planning Report for AUGUST 2024 Issued July 19, 2024
Reissued July 29, 2024
Revision:
RED VALE C.S. TO DOLORES C.S. (Segment 240): Redvale Compressor Station, TransColorado, revises the unit maintenance August 1 through August 8 to August 6 through August 8.
1
RED VALE C.S. TO DOLORES C.S. (Segment 240): Redvale Compressor Station, TransColorado, will be performing unit maintenance August 6 through August 8. This outage results in the following impact.
Dates
Segment
Operating Capacity (MDth/d)
Reduced to Capacity (MDth/d)
TD2 Northbound
August 6 thru August 8
240
260
225
TD1 Southbound
356
342
AUGUST 2024
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
TRANSCOLORADO GAS PIPELINE COMPANY MAINTENANCE
DOLORES C.S. TO MANCOS C.S. (Segment 250): TransColorado will be performing pigging operations Dolores to Red Mesa August 7. This outage results in the following impacts.
August 7
250
0
355
170
DOLORES C.S. TO MANCOS C.S. (Segment 250): Dolores Compressor Station, TransColorado, will be performing Station maintenance August 19 through August 30. This outage results in the following impacts.
August 19 thru August 30
339
Any comments or questions about this report should be directed to Vic Villalva at (719) 520-4251 or Cheryl Bauer at (719) 520-4423.