TRANSCOLORADO Pipeline Company
Operations Planning Report for May 2021
Issued April 20, 2021
TRANSCOLORADO GAS PIPELINE COMPANY MAINTENANCE
1. LA MAQUINA LATERAL TO BLANCO HUB (Segment 310): Blanco Compressor Station, TransColorado will be performing unit maintenance May 5. This outage results in the following impact.
Operating Capacity
Capacity Reduction
Limit MDth/d
May 5 Cycles 1 thru 4
260
150
May 5 Cycle 5
200**
** The nomination limit for this cycle has been prorated for the remaining time in the gas day.
2. LOVE RANCH TO GREASEWOOD (Segment 180): Greasewood Compressor Station, TransColorado will be performing Station DOT/ESD Test and unit shut down checks May 11. This outage results in the following impact.
May 11 Cycles 1 thru 4
571
441
May 11 Cycle 5
501**
3. RACCOON HOLLOW TO LOVE RANCH (Segment 190): Conn Creek Compressor Station, TransColorado will be performing Station DOT/ESD Test and unit shut down checks May 18 through May 21. These outages result in the following impacts.
Northbound
May 18 thru May 20
310
May 21 Cycles 1 thru 4
May 21 Cycle 5
370**
Southbound
365
285
322**
Any comments or questions about this report should be directed to Glen Petty (719) 520-4704.