TRANSCOLORADO Pipeline Company
Operations Planning Report for December 2020
Issued November 16, 2020
TRANSCOLORADO GAS PIPELINE COMPANY MAINTENANCE
1. LA MAQUINA LATERAL TO BLANCO HUB (Segment 310): Blanco Compressor Station, TransColorado will be performing unit maintenance December 1 through December 4. This outage results in the following impacts.
Northbound
Operating Capacity
Capacity Reduction
Limit MDth/d
Dec 1 thru Dec 3
260
150
Dec 4 Cycles 1 thru 4
Dec 4 Cycle 5
200**
** The nomination limit for this cycle has been prorated for the remaining time in the gas day.
Any comments or questions about this report should be directed to Glen Petty (719) 520-4704.