-Restrictions to Primary In-Path transportation services may be necessary.
SNG - Outage Impact Report
-Restrictions to In-Path transportation services may be necessary.
Seven Day Forecast (updated 06/04/26)
-Restrictions to Interruptible and Out of Path transportation services may be necessary.
-No anticipated impact to transportation services.
Station / Seg
Est Nominal Design Capacity (Thousand Dth)
Monday (6/8)
Tuesday (6/9)
Wednesday (6/10)
Thursday (6/11)
Friday (6/12)
Saturday (6/13)
Sunday (6/14)
Primary Outage(s) that may Impact Throughput
Est. Operational Capacity (Operational Impact) - Thousand Dth
Onward (segment 30)
203
Duncanville Lateral (segment 90)
36
Helena Regulator (segment 120)
21
18
(3)
Bessemer Calera Line south of Helena Regulator: Scheduled Pipeline Maintenance Proj-SNG-38163(PT) (M) (5/26/2026 - 7/10/2026)
Dearmanville (segment 150)
346
White Castle (segment 340)
760
685
(75)
Shadyside Compressor Station: Scheduled Unit Maintenance Proj-5000-3 (6/8/2026 - 7/5/2026)
Sesh (segment 380)
507
Gwinville (segment 400)
234
Bay Springs (segment 420)
1,675
1595
(80)
Bay Springs Compressor Station: Scheduled Unit Maintenance Proj-52161 (7/8/2025 - 10/31/2026)
Enterprise (segment 430)
2,306
2166
(140)
Enterprise Compressor Station: Scheduled Unit Maintenance Proj-522212 (3/16/2026 - 6/28/2026)
South Main line east of Enterprise: Unscheduled Pipeline Maintenance - CAO (5/30/2026 - 12/31/2026)
Auburn (segment 460)
1,953
1848
(105)
South Main loop line east of Auburn: Scheduled Pipeline Maintenance(remediation) Proj-SNG-20457(2) (6/8/2026 - 6/19/2026)
Ellerslie (segment 490)
1,547
Thomaston West (segment 490)
1,535
1350
(185)
Thomaston Compressor Station: Scheduled Unit Maintenance Proj-5272-2 (5/27/2026 - 6/26/2026)
Thomaston Compressor Station: Scheduled Unit Maintenance Proj-5272-5 (4/27/2026 - 6/14/2026)
South Atlanta (segment 510)
522
Thomaston East (segment 530)
849
Hall Gate (segment 560)
705
635
(70)
Hall Gate Compressor Station: Scheduled Unit Maintenance Proj-52833 (4/20/2026 - 6/14/2026)
South Georgia (segment 650)
127
This document is updated on a weekly basis and outage schedules/impacts are subject to change as the week progresses. Dates posted on DART should be deemed correct in the event of conflicts between DART posted dates and dates on this report.
The impacts sheet are based on steady-state hydraulic models assuming recent operating flows, conditions, and various unit outages.
June 2026 (updated 06/04/26)
Week 1 (6/1 - 6/7)
Week 2 (6/8 - 6/14)
Week 3 (6/15 - 6/21)
Week 4 (6/22 - 6/28)
Primary Outage(s)
Bessemer Calera Line south of Helena Regulator: Scheduled Pipeline Maintenance,
Proj-SNG-38163(PT) (M) (5/26/2026 - 7/10/2026)
Shadyside Compressor Station: Scheduled Unit Maintenance, Proj-5000-3 (6/8/2026 - 7/5/2026)
White Castle Compressor Station: Scheduled Unit Maintenance, Proj-5010-8 (6/15/2026 - 7/2/2026)
Bay Springs Compressor Station: Scheduled Unit Maintenance,
Proj-52161 (7/8/2025 - 10/31/2026)
Enterprise Compressor Station: Scheduled Unit Maintenance,
Proj-522212 (3/16/2026 - 6/28/2026)
South Main loop line east of Auburn: Scheduled Pipeline Maintenance(remediation),
Proj-SNG-20457(2) (6/8/2026 - 6/19/2026)
Thomaston Compressor Station: Scheduled Unit Maintenance,
1520
(15)
Proj-5272-2 (5/27/2026 - 6/26/2026)
Ocmulgee Compressor Station: Scheduled Unit Maintenance,
Ocmulgee (segment 530)
804
659
(145)
Proj-5277-6 (6/16/2026 - 6/17/2026)
Wrens Compressor Station: Scheduled Unit Maintenance, Proj-5288-4 (6/15/2026 - 7/5/2026)
East/South Wrens (segment 560)
680
585
(95)
This document is updated on a weekly basis and outage schedules/impacts are subject to change as the week progresses.
Dates posted on DART should be deemed correct in the event of conflicts between DART posted dates and dates on this report.
July 2026 (updated 06/04/26)
Week 1 (6/29 - 7/5)
Week 2 (7/6 - 7/12)
Week 3 (7/13 - 7/19)
Week 4 (7/20 - 7/26)
Week 5 (7/27 - 8/2)
Bessemer Calera Line south of Helena Regulator: Scheduled Pipeline Maintenance, Proj-SNG-38163(PT) (M) (5/26/2026 - 7/10/2026)
Bessemer Calera loop line south of Helena Regulator: Scheduled Pipeline Maintenance, Proj-SNG-38163(PT) (M) (7/16/2026 - 9/3/2026)
Tarrant (segment 130)
563
438
(125)
North Main loop line east of Providence: Scheduled Pipeline Maintenance(remediation), Proj-SNG-20462/SNG-21973 (7/6/2026 - 8/14/2026)
Shadyside Compressor Station: Scheduled Unit Maintenance, Proj-5000-3 (6/8/2026 - 7/5/2026) White Castle Compressor Station: Scheduled Unit Maintenance,
Proj-5010-8 (6/15/2026 - 7/2/2026)
500
Bay Springs Compressor Station: Scheduled Unit Maintenance, Proj-52161 (7/8/2025 - 10/31/2026)
2126
(180)
Enterprise Compressor Station: Scheduled Unit Maintenance, Proj-522215 (6/29/2026 - 8/2/2026)
York
'ZONE 1/2 BOUNDARY'
(segment 440)
2,305
2135
(170)
South Main 2nd loop line east of York: Scheduled Pipeline Maintenance, Proj-SNG-36214 (7/6/2026 - 7/15/2026)
590
(90)
Wrens Compressor Station: Scheduled Unit Maintenance, Proj-5288-4 (6/15/2026 - 7/5/2026) Wrens Compressor Station: Scheduled Unit Maintenance, Proj-52885 (7/13/2026 - 7/19/2026)
Dates posted on DART should be deemed correct in the event of conflicts between DART posted dates and dates on this report. The impacts sheet are based on steady-state hydraulic models assuming recent operating flows, conditions, and various unit outages.
August 2026 (updated 06/04/26)
Week 1 (8/3 - 8/9)
Week 2 (8/10 - 8/16)
Week 3 (8/17 - 8/23)
Week 4 (8/24 - 8/30)
Bessemer Calera loop line south of Helena Regulator: Scheduled Pipeline Maintenance,
Proj-SNG-38163(PT) (M) (7/16/2026 - 9/3/2026)
North Main loop line east of Providence: Scheduled Pipeline Maintenance(remediation),
543
(20)
Proj-SNG-20462/SNG-21973 (7/6/2026 - 8/14/2026)
Tarrant Compressor Station: Scheduled Unit Maintenance(panel), Proj-4152-7-8-9-14 (8/3/2026 - 9/27/2026)
South Main line east of Enterprise: Unscheduled Pipeline Maintenance - CAO
(5/30/2026 - 12/31/2026)
Ellerslie Compressor Station: Scheduled Station Maintenance, Proj-5267 (8/18/2026 - 8/20/2026)
1317
(230)
September 2026 (updated 06/04/26)
Week 1 (8/31 - 9/6)
Week 2 (9/7 - 9/13)
Week 3 (9/14 - 9/20)
Week 4 (9/21 - 9/27)
Tarrant Compressor Station: Scheduled Unit Maintenance(panel),
Proj-4152-7-8-9-14 (8/3/2026 - 9/27/2026)
Pickens Compressor Station: Scheduled Unit Maintenance, Proj-4125-2 (8/31/2026 - 9/23/2026)
154
Gallion Compressor Station: Scheduled Unit Maintenance, Proj-5236-9 (9/7/2026 - 9/27/2026)
Gallion (Segment 440)
2,300
2145
(155)
2255
(45)
South Main loop line east of Gallion: Scheduled Pipeline Maintenance(remediation), Proj-SNG-22002 (9/7/2026 - 9/18/2026)
Selma Compressor Station: Scheduled Unit Maintenance, Proj-52453 (9/14/2026 - 9/20/2026)
Selma (segment 460)
2,293
1973
(320)
Wrens Compressor Station: Scheduled Unit Maintenance, Proj-5288-4 (9/8/2026 - 9/11/2026)