-Restrictions to Primary In-Path transportation services may be necessary.
SNG - Outage Impact Report
-Restrictions to In-Path transportation services may be necessary.
Seven Day Forecast (updated 11/06/25)
-Restrictions to Interruptible and Out of Path transportation services may be necessary.
-No anticipated impact to transportation services.
Station / Seg
Est Nominal Design Capacity (Thousand Dth)
Monday (11/10)
Tuesday (11/11)
Wednesday (11/12)
Thursday (11/13)
Friday (11/14)
Saturday (11/15)
Sunday (11/16)
Primary Outage(s) that may Impact Throughput
Est. Operational Capacity (Operational Impact) - Thousand Dth
Onward (segment 30)
209
Louisville East (segment 50)
520
203
(317)
Louisville Compressor Station: Scheduled Station Maintenance Proj-4132HS (11/10/2025 - 11/15/2025)
Duncanville Lateral (segment 90)
36
Dearmanville (segment 150)
355
White Castle (segment 340)
798
728
(70)
598
(200)
Duck Lake Franklinton Line north of White Castle: Scheduled Pipeline Maintenance Proj-SNG-22856 (11/11/2025 - 11/22/2025)
White Castle Compressor Station: Scheduled Unit Maintenance Proj-50109 (11/10/2025 - 12/6/2025)
LA West Leg (segment 350)
540
(258)
White Castle Franklinton loop line north of White Castle: Pipeline Maintenance(replacement) Proj-SNG-2993 (10/14/2025 - 11/10/2025)
Sesh (segment 380)
506
Gwinville (segment 400)
234
174
(60)
Pickens Compressor Station: Unscheduled Unit Maintenance Proj-41252 (10/12/2025 - 11/16/2025)
Bay Springs (segment 420)
1,887
1647
(240)
1487
(400)
Bay Springs Compressor Station: Scheduled Unit Maintenance Proj-52161 (7/8/2025 - 3/31/2026)
Bay Springs Compressor Station: Scheduled Unit Maintenance Proj-52163 (11/12/2025 - 11/15/2025)
Enterprise (segment 430)
2,450
2365
(85)
2425
(25)
Enterprise Compressor Station: Scheduled Unit Maintenance Proj-522210 (11/12/2025 - 11/15/2025)
Enterprise Compressor Station: Scheduled Unit Maintenance Proj-522211 (11/3/2025 - 11/11/2025)
Ellerslie (segment 490)
1,663
Thomaston West (segment 490)
1,650
1605
(45)
1460
(190)
Thomaston Compressor Station: Scheduled Pipeline Maintenance(valve replacement) Proj-5272 (11/3/2025 - 11/14/2025)
Thomaston Compressor Station: Scheduled Station Maintenance(valve replacement) Proj-5272 (11/12/2025 - 11/13/2025)
South Atlanta (segment 510)
537
Thomaston East (segment 530)
900
Hall Gate (segment 560)
700
606
(94)
South Main Line east of Hall Gate: Unscheduled Pipeline Maintenance(remediation) Proj-SNG-21445 (10/28/2025 - 12/14/2025)
East/South Wrens (segment 560)
724
554
(170)
Wrens Compressor Station: Scheduled Maintenance Proj-52885 (11/6/2025 - 11/16/2025)
South Georgia (segment 650)
143
Albany (segment 660)
77
(41)
Albany Compressor Station: Scheduled Station Maintenance Proj-58171 (10/20/2025 - 11/14/2025)
This document is updated on a weekly basis and outage schedules/impacts are subject to change as the week progresses.
Dates posted on DART should be deemed correct in the event of conflicts between DART posted dates and dates on this report. The impacts sheet are based on steady-state hydraulic models assuming recent operating flows, conditions, and various unit outages.
November 2025 (updated 11/06/25)
Week 1 (11/3 - 11/9)
Week 2 (11/10 - 11/16)
Week 3 (11/17 - 11/23)
Week 4 (11/24 - 11/30)
Primary Outage(s)
590
(208)
Duck Lake Franklinton Line north of White Castle: Scheduled Pipeline Maintenance, Proj-SNG-22856 (11/11/2025 - 11/22/2025)
White Castle Compressor Station: Scheduled Unit Maintenance, Proj-50109 (11/10/2025 - 12/6/2025) White Castle Franklinton Loop Line north of White Castle: Scheduled Pipeline Maintenance, Proj-SNG- 22856 (11/23/2025 - 12/4/2025)
Bay Springs Compressor Station: Scheduled Unit Maintenance, Proj-52161 (7/8/2025 - 3/31/2026)
2395
(55)
Enterprise Compressor Station: Scheduled Unit Maintenance, Proj-522211-13 (11/17/2025 - 11/21/2025)
Elmore (segment 460)
2,155
1930
(225)
Elmore Compressor Station: Scheduled Unit Maintenance, Proj-525112 (11/17/2025 - 11/24/2025)
South Main Line east of Hall Gate: Unscheduled Pipeline Maintenance(remediation), Proj-SNG-21445 (10/28/2025 - 12/14/2025)
Dates posted on DART should be deemed correct in the event of conflicts between DART posted dates and dates on this report.
The impacts sheet are based on steady-state hydraulic models assuming recent operating flows, conditions, and various unit outages.
December 2025 (updated 11/06/25)
Week 1 (12/1 - 12/7)
Week 2 (12/8 - 12/14)
Week 3 (12/15 - 12/21)
Week 4 (12/22 - 12/28)
500
January 2026 (updated 11/06/25)
Week 1 (12/29 - 1/4)
Week 2 (1/5 - 1/11)
Week 3 (1/12 - 1/18)
Week 4 (1/19 - 1/25)
Week 5 (1/26 - 2/1)
February 2026 (updated 11/06/25)
Week 1 (2/2 - 2/8)
Week 2 (2/9 - 2/15)
Week 3 (2/16 - 2/22)
Week 4 (2/23 - 3/1)