Update #2- Scheduled Pipeline maintenance -Duck Lake Franklinton Line (Segment 350)
The scheduled pipeline maintenance on the Duck Lake Franklinton line north of White Castle compressor that was scheduled through September 4th, 2024, has been extended to October 11th, 2024. As a result of this Segment 350 (LA West Leg) capacity of 735 Mdth/d will remain reduced by 15 Mdth/d.
In addition, due to this extension, the pipeline maintenance on the White Castle Franklinton loop line scheduled for October 4th, 2024, through November 1st, 2024, is now scheduled for October 12th, 2024, through November 11th, 2024. During this outage, Segment 350 (LA West Leg) capacity of 735Mdth/d will be impacted 200 Mdth/d.
Please reference our weekly EBB postings and posting (709864) posted on September 26th, 2024.
If you have any questions, please call your Account Manager or Scheduling Representative.
SNG Gas Control