-Restrictions to Primary In-Path transportation services may be necessary.
SNG - Outage Impact Report
-Restrictions to In-Path transportation services may be necessary.
Seven Day Forecast (updated 09/10/20)
-Restrictions to Interruptible and Out of Path transportation services may be necessary.
-No anticipated impact to transportation services.
Station / Seg
Est Nominal Design Capacity (Thousand Dth)
Monday (9/14)
Tuesday (9/15)
Wednesday (9/16)
Thursday (9/17)
Friday (9/18)
Saturday (9/19)
Sunday (9/20)
Primary Outage(s) that may Impact Throughput
Est. Operational Capacity (Operational Impact) - Thousand Dth
Onward (segment 30)
203
Duncanville Lateral (segment 90)
37
Dearmanville (segment 150)
346
275
(71)
Dearmanville compressor station: Unit Maintenance (9/14/2020 - 10/8/2020)
White Castle (segment 340)
701
Sesh (segment 380)
507
Gwinville (segment 400)
234
115
(119)
Gwinville compressor station: Unit maintenance (7/20/2020 - 10/8/2020) Rankin compressor station: Unit Maintenance (8/3/2020 - 9/25/2020) Pickens compressor station: Unit Maintenance (8/31/2020 - 9/25/2020)
Enterprise (segment 430)
2,283
2198
(85)
Enterprise compressor station: Controls Upgrade (6/8/2020 - 11/6/2020)
Ellerslie (segment 490)
1,547
South Atlanta (segment 510)
522
Thomaston East (segment 530)
849
South Georgia (segment 650)
127
This document is updated on a weekly basis and outage schedules/impacts are subject to change as the week progresses.
Dates posted on DART should be deemed correct in the event of conflicts between DART posted dates and dates on this report. The impacts sheet are based on steady-state hydraulic models assuming recent operating flows, conditions, and various unit outages.
SNG-OutageImpactReport
September 2020 (updated 09/10/20)
EstNominalDesign Capacity (ThousandDth)
Week 1 (8/31 - 9/6)
Week 2 (9/7 - 9/13)
Week 3 (9/14 - 9/20)
Week 4 (9/21 - 9/27)
Primary Outage(s)
Shady Side and White Castle compressor stations: Unit Maintenance (9/21/2020 - 10/31/2020)
601
(100)
Gwinville compressor station: Unit maintenance (7/20/2020 - 10/8/2020)
Rankin compressor station: Unit Maintenance (8/3/2020 - 9/25/2020) Pickens compressor station: Unit Maintenance (8/31/2020 - 9/25/2020)
Dates posted on DART should be deemed correct in the event of conflicts between DART posted dates and dates on this report.
The impacts sheet are based on steady-state hydraulic models assuming recent operating flows, conditions, and various unit outages.
October 2020 (updated 09/10/20)
Week 1 (9/28 - 10/4)
Week 2 (10/5 - 10/11)
Week 3 (10/12 - 10/18)
Week 4 (10/19 - 10/25)
Week 5 (10/26 - 11/1)
Reform (segment 90)
686
480
(206)
North main loop line/North main line east of Lousiville: Make piggable (10/13/2020 - 10/31/2020)
Pell City Station (segment 140)
474
369
(105)
Pell City compressor station: Compressor Station Maintenance (10/6/2020 - 10/7/2020)
141
(205)
Dearmanville compressor station: Unit Maintenance (9/14/2020 - 10/8/2020) DeArmanville compressor station: Valve Replacement (10/5/2020)
Bell Mills North (Segment 170)
232
123
(109)
Bell Mills compressor station: Controls Upgrade (10/9/2020 - 10/13/2020)
551
(150)
Shady Side and White Castle compressor stations: Unit Maintenance (9/7/2020 - 10/31/2020) White Castle compressor station: Station maintenance (10/13/2020)
167
(67)
Gwinville compressor station: Unit maintenance (7/20/2020 - 10/8/2020) Rankin compressor station: Unit Maintenance (9/28/2020 - 10/23/2020)
York (segment 440)
1900
(383)
York compressor station: Unit Maintenance (10/5/2020 - 11/5/2020)
November 2020 (updated 09/10/20)
Week 1 (11/2 - 11/8)
Week 2 (11/9 - 11/15)
Week 3 (11/16 - 11/22)
Week 4 (11/23 - 11/29)
209
355
798
508
2,427
(229)
(527)
1,663
537
900
143
December 2020 (updated 09/10/20)
Week 1 (11/30 - 12/6)
Week 2 (12/7 - 12/13)
Week 3 (12/14 - 12/20)
Week 4 (12/21 - 12/27)
Week 5 (12/28 - 1/3)