-Restrictions to Primary In-Path transporation services may be necessary.
SNG - Outage Impact Report
-Restrictions to In-Path transporation services may be necessary.
Seven Day Forecast (updated 07/30/20)
-Restrictions to Interuptable and Out of Path transportation services may be necessary.
-No anticipated impact to transportation services.
Station / Seg
Est Nominal Design Capacity (Thousand Dth)
Monday (8/3)
Tuesday (8/4)
Wednesday (8/5)
Thursday (8/6)
Friday (8/7)
Saturday (8/8)
Sunday (8/9)
Primary Outage(s) that may Impact Throughput
Est. Operational Capacity (Operational Impact) - Thousand Dth
Onward (segment 30)
203
Duncanville Lateral (segment 90)
37
Dearmanville (segment 150)
346
White Castle (segment 340)
701
Sesh (segment 380)
508
449
(59)
SESH system west of Gwinville: SESH unit Maintenance (M) (8/1/2020 - 8/3/2020)
Gwinville (segment 400)
234
167
(67)
Gwinville compressor station: Unit maintenance (7/20/2020 - 10/8/2020) Rankin compressor station: Unit Maintenance (8/3/2020 - 8/28/2020)
Enterprise (segment 430)
2,283
2198
(85)
Enterprise compressor station: Controls Upgrade (6/8/2020 - 11/6/2020)
Ellerslie (segment 490)
1,547
South Atlanta (segment 510)
522
Thomaston East (segment 530)
849
South Georgia (segment 650)
127
This document is updated on a weekly basis and outage schedules/impacts are subject to change as the week progresses.
Dates posted on DART should be deemed correct in the event of conflicts between DART posted dates and dates on this report. The impacts sheet are based on steady-state hydraulic models assuming recent operating flows, conditions, and various unit outages.
August 2020 (updated 07/30/20)
Week 1 (8/3 - 8/9)
Week 2 (8/10 - 8/16)
Week 3 (8/17 - 8/23)
Week 4 (8/24 - 8/30)
Primary Outage(s)
Auburn (segment 460)
1,943
1898
(45)
Auburn compressor station: Unit Maintenance (8/24/2020 - 9/3/2020)
Dates posted on DART should be deemed correct in the event of conflicts between DART posted dates and dates on this report.
The impacts sheet are based on steady-state hydraulic models assuming recent operating flows, conditions, and various unit outages.
September 2020 (updated 07/30/20)
Week 1 (8/31 - 9/6)
Week 2 (9/7 - 9/13)
Week 3 (9/14 - 9/20)
Week 4 (9/21 - 9/27)
275
(71)
Dearmanville compressor station: Unit Maintenance (9/14/2020 - 10/8/2020)
601
(100)
Shady Side and White Castle compressor stations: Unit Maintenance (9/1/2020 - 10/31/2020)
115
(119)
Gwinville compressor station: Unit maintenance (7/20/2020 - 10/8/2020) Pickens compressor station: Unit Maintenance (8/31/2020 - 9/25/2020) Rankin compressor station: Unit Maintenance (8/31/2020 - 9/25/2020)
October 2020 (updated 07/30/20)
Week 1 (9/28 - 10/4)
Week 2 (10/5 - 10/11)
Week 3 (10/12 - 10/18)
Week 4 (10/19 - 10/25)
Week 5 (10/26 - 11/1)
Reform (segment 90)
686
480
(206)
North main loop line/North main line east of Lousiville: Make piggable (10/13/2020 - 10/31/2020)
Bell Mills North (Segment 170)
232
123
(109)
Bell Mills compressor station: Controls Upgrade (10/9/2020 - 10/13/2020)
Gwinville compressor station: Unit maintenance (7/20/2020 - 10/8/2020)
York (segment 440)
1900
(383)
York compressor station: Unit Maintenance (10/5/2020 - 11/5/2020)
November 2020 (updated 07/30/20)
Week 1 (11/2 - 11/8)
Week 2 (11/9 - 11/15)
Week 3 (11/16 - 11/22)
Week 4 (11/23 - 11/29)
209
355
798
2,427
(229)
(527)
1,663
537
900
143