Subject:  Operations Planning Report June 2022
Notice Text:

Ruby Pipeline Company

Operations Planning Report for June 2022

Issued May 18, 2022

RUBY PIPELINE COMPANY MAINTENANCE

Nevada

1. WIELAND FLAT TO NV/OR ST LINE (Segment 50):  Desert Valley Compressor Station ESD Test on June 7 and unit shut down checks on June 8. This outage results in the following impact.

Operating Capacity

Capacity Reduction

Limit MDth/d

Limit MDth/d

June 7 Cycles 1 thru 4

1,489

1,228

June 7 Cycle 5

1,489

    1,348**

June 8 Cycles 1 thru 4

1,489

1,228

June 8 Cycle 5

1,489

    1,348**

** The nomination limit for this cycle has been prorated for the remaining time in the gas day.

2. WIELAND FLAT TO NV/OR ST LINE (Segment 50): Wieland Compressor Station ESD Test on June 14 and unit shut down checks one unit at a time on June 15 and June 16.  This outage results in the following impact.

Operating Capacity

Capacity Reduction

Limit MDth/d

Limit MDth/d

June 14 Cycles 1 thru 4

1,489

1,204

June 14 Cycle 5

1,489

    1,335**

June 15 Cycles 1 thru 4

1,489

1,391

June 15 Cycle 5

1,489

    1,436**

June 16 Cycles 1 thru 4

1,489

1,391

June 16 Cycle 5

1,489

    1,436**

** The nomination limit for this cycle has been prorated for the remaining time in the gas day.

Any comments or questions about this report should be directed to Glen Petty (719) 520-4704 or Vic Villalva (719) 520-4251.