REVISED – DATE CORRECTION
PHP is preparing for its first baseline pigging and 4,000 hour compressor inspections to be completed throughout the month of June. Our still tentative schedule will require PHP's available capacity to be reduced from 2.1 BCF down to 1.0 BCF during the periods of work as outlined below.
Tuesday June 8th through Friday June 12th PHP's available capacity will be limited to 1.0 BCF/day.
Saturday June 12th through Monday June 14th PHP's available capacity will return to 2.1 BCF/day.
Tuesday June 15th through Friday June 18th PHP's available capacity will again be limited to 1.0 BCF/day.
Saturday June 19th through Wednesday June 23rd PHP's available capacity will return to normal at 2.1 BCF/day.
Thursday June 24th (one day only) PHP's available capacity will again be limited to 1.0 BCF/day.
Friday June 25th we expect all work to be completed and PHP's available capacity will return to 2.1 BCF/day.
While this schedule remains tentative, we are working to secure the necessary resources to ensure this schedule is firmed up and ultimately successful. PHP will notify everyone if this schedule gets modified in any way and we plan on having a final schedule distributed by mid-May.
PHP's appreciates your understanding and cooperation with this necessary maintenance.
Please contact your scheduling representative if you have any questions or concerns regarding the schedule.