SEGMENT 11 - AMARILLO #4 MAINLINE – ILI TOOL RE-RUN – UPDATE 1
The tool run date has been changed, as noted below. See previous Notice ID 46019 dated May 14, 2025.
As posted on Natural's Outage Impact Report (X24-1152095) and as part of Natural's ongoing pipeline Integrity Management Program, Natural is required to re-run its ILI Tool – EMAT near Compressor station 193 (CS 193) located in Edwards County, Kansas. This re-run is due to an internal equipment failure in the tool. The tool re-run will require Natural to limit the following location listed below for the duration of the restriction.
As such, effective on the gas day indicated below, the location listed below will be scheduled to Primary Firm transports only. AOR/ITS, Secondary out-of-path Firm transports and Secondary in-path Firm transports will not be available.
TOOL RUN DATE:
Gas day Thursday, July 17, 2025 (previously Tuesday, July 15, 2025) (EMAT Tool)
LOCATION:
LOC 41543 CPG/NGPL FORD
Once the data from the tool run have been analyzed, any remediation work impacting shippers will be posted. Continue to monitor Natural's interactive website for any updates. Please contact your Account Director or Scheduling Representative if you have any questions.