SEGMENT 23 – COMPRESSOR STATION 342 – INSTALL LAUNCHER AND RECEIVER – UPDATE 1
The outage dates have been changed, as noted below. See previous Notice ID 45497 dated October 14, 2024.
As previously posted on Natural's Outage Impact Report (X24-809820) as no impact, Natural will be installing a launcher and receiver at Compressor Station 342 (CS 342), in Cameron Parish, Louisiana (Segment 23 of Natural's Louisiana Zone). As a result, Natural is required to shut-in the locations as noted below for the duration of this restriction. No transport services are available.
UNAVAILABLE DATES:
Gas day Tuesday, October 15, 2024, Timely Cycle and continuing through gas day Monday, November 18, 2024 (previously Friday, November 8, 2024). However, the Bridgeline Johnsons Bayou (LOC 44094) related work will be completed earlier than anticipated, as noted below.
LOCATIONS IMPACTED:
LOC 44094 BRIDGELINE JOHNSONS BAYOU (Available gas day Wednesday, October 30, 2024)
LOC 40300 HILCORP CAMERON (Unavailable through gas day Monday, November 18, 2024)
Please contact your Account Director or Scheduling Representative if you have any questions.