August 12, 2024
The restriction at the Los Ramones delivery point has been lifted. Full capacity was restored the afternoon of Thursday, August 8, 2024.
July 18, 2024
Due to a delay in receiving the parts needed to repair the facility, the maintenance at the Los Ramones delivery point has been delayed. In the interim, NET Mexico Pipeline Partners, LLC (NET Mexico) has reevaluated current operating conditions and is lifting the restriction from 1,700,000 MMBtu/d to 1,750,000 MMBtu/d, effective for the Gas Day of July 19, 2024. NET Mexico will post updates as more information on the completion date becomes available.
June 21, 2024
NET Mexico Pipeline Partners, LLC (NET Mexico) wishes to inform its customers that the completion date has been extended due to a delay in receiving parts. The completion is now expected to be approximately July 25, 2024. NET Mexico will post updates as we receive more information on the completion date
May 31, 2024
NET Mexico Pipeline Partners, LLC (NET Mexico) wishes to inform its customers that the completion date for the repair below has been extended to approximately 30 days from today. NET Mexico will post updates as we receive more information on the completion date
May 15, 2024
NET Mexico Pipeline Partners, LLC (NET Mexico) wishes to inform its customers that due to an unexpected repair of one of the meter runs going to the Los Ramones delivery point, the capacity at the Los Ramones point will be limited to 1,700,000 MMBtu/d effective May 15, 2024. The restriction is expected to last approximately 2 weeks. NET Mexico will post updates as we receive more information on the completion date