Devils River C/S Inspection Posting:
Planned Compressor Outage
Gulf Coast Express Pipeline LLC ("GCX") wishes to inform its customers that due to manufacturer-required inspections of compressors, the total capacity on GCX will be reduced to 1,670,000 MMBtu. The firm shippers will be prorated based on their FIRM MDQ and will be notified by their account representative.
The reduction will begin April 20, 2021 and is expected to be back to full capacity on April 24, 2021.
GCX will post updates if there are any changes to this schedule. We appreciate your cooperation at this time. Should you have any questions concerning the foregoing, please do not hesitate to contact your commercial representative.