On February 28, 2025, Cheyenne Plains Gas Pipeline Company, L.L.C. (CPG) filed with the Federal Energy Regulatory Commission ("FERC")
to adjust the Fuel and Lost and Unaccounted-for-Gas ("FL&U") reimbursement percentages and the Electric Power Cost ("EPC") charge pursuant to General Terms and Conditions, Sections 13 and 30 of CPG's First Revised Volume No. 1 FERC Gas Tariff with a proposed effective date of April 1, 2025 as shown below:
FL&U REIMBURSEMENT (% OF RECEIPT VOLUME)
Fuel 0.42*
Lost and Unaccounted 0.23*
------
Total 0.65
EPC CHARGE ($ PER DTH OF DELIVERY VOLUME)
EPC Charge $0.000*
*The FL&U percentages and EPC reimbursement rate have been filed at FERC in Docket No. RP25-651-000.
If you have any questions about the subject adjustments, the point of contact is below or contact your CPG Account Representative.
Dan Tygret
Director, Marketing
(719) 520-3765