Colorado Interstate Gas Company
Operations Planning Report May 2026
Re-issued April 21, 2026
Pipe
Start Date
End Date
County, ST
Scheduling Location
Maintenance List
Base Capacity (Dth)
Reduction (Dth)
Net (Dth)
Flow Indication
Update
CIG
5/14/26
5/21/26
MORTON, KS
800715 (TCS) STORAGE INJ/WTD
Boehm Storage - Spring BHP Survey no injection or withdrawal Reference Spring Storage Notice #122874
5/19/26
UINTA, WY
100_KING CS TO EMERALD SPRINGS
King Station DOT/ESD Test
153,000
0
TD1
CARBON, WY
132_(RSWC) RAWLINS WEST
Rawlins Station DOT/ESD Test
600,000
130,000
470,000
136_LOST CABIN CS TO WILD HORSE
Addition Rawlins Station DOT/ESD Test - Station Maintenance
45,000
5/27/26
PARK, WY
144_(OBLC) OREGON BASIN LATERAL
Oregon Station DOT/ESD Test
21,000
6/3/26
MORGAN,CO
80007 YGS/CIG (BCS) BIJOU CREEK RECEIPT M
Young Storage - Spring BHP Survey no injection or withdrawal Reference Spring Storage Notice #122912
800826 YGS/CIG (YCS) YOUNG GAS STORAGE MOR
5/1/26
5/31/26
LARAMIE,WY
164_(CHWC) CHEYENNE WEST
Reference Notice# 122918 Notice of Force Majeure – Segment 164 Line 5A pipeline Cheyenne to Laramie investigation and repair
570,000
223,000
347,000
164_(CHWC) CHEYENNE WEST_BH
315,000
80,000
235,000
TD2
In addition to planned outages, this report reflects the repairs and maintenance being performed related to Force Majeure events.
Due to the nature of such events, the dates for the associated repairs and maintenance of those events are assumed to extend until the end of the month.
These repairs and maintenance, however, may extend beyond the end of the month including beyond the current year.
More information on these repairs and maintenance will be posted as a Critical Notice under the Notices section of the Informational Postings tab on the CIG Electronic Bulletin Board