Pipe
Start Date
End Date
County, ST
Scheduling Location
Maintenance List
Base Capacity (Dth)
Reduction (Dth)
Net (Dth)
Flow Indication
Update
CIG
2/1/25
2/28/25
MORGAN, CO
260_(WTEC) WATKINS EAST
Line 2A & 2B pipeline maintenance Watkins to MLV 23 one line at a time
398,000
132,000
266,000
TD1
260_(WTEC) WATKINS EAST_BH
365,000
92,000
273,000
TD2
2/18/25
2/19/25
PARK, WY
142_(BHNC) BIG HORN NORTH
Addition Elk Basin Unit 1 maintenance
117,000
27,000
90,000
2/24/25
BEAVER, OK
288_BAKER MS TO BEAVER CS
Addition Beaver Unit 1 maintenance
305,000
140,000
165,000
800078_ANR/CIG (BEA) BEAVER
227,000
127,000
100,000