Addition:
800229: Elk Basin WBI/CIG (ELK) Elk Basin Park - CIG will be performing pipeline maintenance on Line 139A for make piggable project. During this time, no receipt flow will be received from this location.
2. 800229: Elk Basin WBI/CIG (ELK) Elk Basin Park: CIG will be performing pipeline maintenance on Line 139A for make piggable project. During this time, no receipt flow will be received from this location.
Operating Capacity
Capacity Reduction
Limit MDth/d
August 16 thru August 21
113
0
August 22 Cycles 1 thru 4
August 22 Cycle 5
57**
** The nomination limit for this cycle has been prorated for the remaining time in the gas day.
Colorado Interstate Gas Company
Operations Planning Report for August 2022
Issued July 19, 2022
ReIssued August 5, 2022
COLORADO INTERSTATE GAS COMPANY MAINTENANCE
South of Springfield, CO (including Texas and Oklahoma):
1. Baker MS TO Beaver CS (Segment 288): Beaver Compressor Station one unit will be out of service August 9 through August 11 to perform mechanical maintenance. This outage will result in the following impact.
August 9 thru August 10
305
242
August 11 Cycles 1 thru 3
August 11 Cycles 4 thru 5
281**
Wyoming:
2. 800229: Elk Basin WBI/CIG (ELK) Elk Basin Park: CIG will be performing pipeline maintenance on Line 139A for make piggable project. During this time no receipt flow will be received from this location.
Colorado: None of the planned maintenance is expected to impact service.
Utah: None of the planned maintenance is expected to impact service.
Kansas: None of the planned maintenance is expected to impact service.
CIG Storage Guidelines
Storage inventory is projected to be within normal guidelines on August 1.
Field Max Inject., MMcf/d Max. Withdraw MMcf/d Boehm 65,000 124,000 Flank 50,000 164,000 Ft. Morgan 110,000 450,000 Latigo 70,000 139,000 Totals 295,000 877,000
Note to storage table: Maximum injection and withdrawal figures are based upon projections for gas-in-place on August 1, 2022. Departure from these projections can affect injection and withdrawal capabilities. Thermal quantities related to storage field transactions are determined based upon an average of 1090 Btu/cf.
CIG Services Utilizing Young Gas Storage Company
None of the planned maintenance is expected to impact service.
No Planning Meeting Scheduled
No requests for a Joint Monthly Operating Plan Meeting have been received by CIG. Therefore, pursuant to Section 11.1 of General Terms and Conditions of the FERC Gas Tariff, no such meetings have been scheduled. If at any time there are any questions regarding operational issues, do not hesitate to call Glen Petty at (719) 520-4704.
Any comments or questions about this report should be directed to Glen Petty (719) 520-4704 or Vic Villalva (719) 520-4251.