Revision:
BLUE FOREST TO GREEN RIVER (SEGMENT 104): 150A - 20" CIG updates the pipeline maintenance is extended April 15 through April 22
2. BLUE FOREST TO GREEN RIVER (SEGMENT 104): 150A - 20" CIG will be performing pipeline maintenance April 15 through April 22. Volumes west of segment 104 will need to net to zero.
Backhaul
Operating Capacity
Capacity Reduction
Limit MDth/d
April 15 thru April 22
70
0
Colorado Interstate Gas Company
Operations Planning Report for April 2021
Issued March 19, 2021
Reissued April 18, 2021
COLORADO INTERSTATE GAS COMPANY MAINTENANCE
Wyoming:
1. ELK /BIG HORN TO OREGON BASIN (Segment 142): Elk Basin Compressor Station, CIG will be performing unit maintenance April 14. Capacity through Segment 142 will vary during this outage. Operating conditions and system loading on the Big Horn Lateral/Wind River Lateral supporting deliveries to WBI/CIG (Elk) Elk Basin Park (800229) and NWC/CIG (GRZ) Grizzly Meter Station (800284) may fluctuate. As a result the operationally available capacity at Segment 142 will range between 55 MDthd to 90 MDthd. The capacity available will be based on CIG's evaluation of operating conditions at that time.
Colorado: None of the planned maintenance is expected to impact service.
Utah: None of the planned maintenance is expected to impact service
Kansas: None of the planned maintenance is expected to impact service
South of Springfield, CO (including Texas and Oklahoma):
3.CAMPO RS TO CO/OK ST LINE (Segment 292): 3A - 20" CIG will be performing pipeline remediation April 12 through April 26 .The outage results in the impact
April 12 thru April 26
190
105
4. EPNG/CIG (BIG) BIG BLUE MOORE (800089): 3A - 20" CIG will be performing pipeline remediation April 12 through April 26 See (Item 3) Big Blue Delivery will be unavailable and Big Blue Receipt will be available for scheduling. This outage results in the following impact.
240
CIG Storage Guidelines
Storage inventory is projected to be within normal guidelines on April 1.
Field Max Inject., MMcf/d Max. Withdraw MMcf/d Boehm 65,000 65,000 Flank 65,000 110,000 Ft. Morgan 150,000 300,000 Latigo 75,000 65,000 Totals 355,000 540,000
Note to storage table: Maximum injection and withdrawal figures are based upon projections for gas-in-place on April 1, 2021. Departure from these projections can affect injection and withdrawal capabilities. Thermal quantities related to storage field transactions are determined based upon an average of 1090 Btu/cf.
Field maintenance is scheduled during April for each of the storage reservoirs. Please refer to posting #119720 for additional information about the injection limitations based on the expected work schedule.
Additionally, field maintenance is scheduled during April for Totem storage reservoir. Please refer to Notice #119802 for additional information about the injection limitations based on the expected work schedule.
CIG Services Utilizing Young Gas Storage Company
None of the planned maintenance is expected to impact service
No Planning Meeting Scheduled
No requests for a Joint Monthly Operating Plan Meeting have been received by CIG. Therefore, pursuant to Section 11.1 of General Terms and Conditions of the FERC Gas Tariff, no such meetings have been scheduled. If at any time there are any questions regarding operational issues, do not hesitate to call Glen Petty (719) 520-4704
Any comments or questions about this report should be directed to Glen Petty (719) 520-4704