TSP/TSP Name:  6914865-COLORADO INTERSTATE GAS CO. Critical: Y
Notice Type Desc (1):  MAINTENANCE Notice Type Desc (2):  MAINTENANCE
Notice Eff Date/Time:  01/19/2021 2:02:17PM Notice End Date/Time:  02/18/2021 9:00:00am
Post Date/Time:  1/19/2021 2:02:17 PM Notice ID: 119703
Reqrd Rsp:  1 Rsp Date:  01/19/2021
Notice Stat Desc:  INITIATE Prior Notice: 
Subject:  Operations Planning Report February 2021
Notice Text:

Colorado Interstate Gas Company

Operations Planning Report for February 2021

Issued January 19, 2021

COLORADO INTERSTATE GAS COMPANY MAINTENANCE

Wyoming:

1. WBI/CIG (ELK) ELK BASIN PARK (800229): Will be out of service for 12 hours February 17 to perform the Elk Basin Compressor Station maintenance. This outage will result in the following impact.

Operating Capacity

Capacity Reduction

Limit MDth/d

Limit MDth/d

February 17 Cycles 1 thru 4

114

0

February 17 Cycle 5

114

52**

** The nomination limit for this cycle has been prorated for the remaining time in the gas day.

Colorado: None of the planned maintenance is expected to impact service.

Utah: None of the planned maintenance is expected to impact service

Kansas: None of the planned maintenance is expected to impact service

CIG Storage Guidelines

Storage inventory is projected to be within normal guidelines on February 1.

Field   

Max Inject MMcf/d

 Max. Withdraw MMcf/d

Boehm

60,000

124,000

Flank

45,000

164,000

Ft. Morgan

100,000

450,000

Latigo

55,000

139,000

Totals

260,000

877,000

Note to storage table: Maximum injection and withdrawal figures are based upon projections for gas-in-place on February 1, 2021. Departure from these projections can affect injection and withdrawal capabilities. Thermal quantities related to storage field transactions are determined based upon an average of 1064 Btu/cf.

CIG Services Utilizing Young Gas Storage Company

 None of the planned maintenance is expected to impact service

No Planning Meeting Scheduled

No requests for a Joint Monthly Operating Plan Meeting have been received by CIG. Therefore, pursuant to Section 11.1 of General Terms and Conditions of the FERC Gas Tariff, no such meetings have been scheduled. If at any time there are any questions regarding operational issues, do not hesitate to call Glen Petty at (719)520-4704.

Any comments or questions about this report should be directed to Glen Petty (719) 520-4704.

 

..