ARLINGTON STORAGE FACILITY MAINTENANCE UPDATE #1
The Thomas Corners Well Maintenance project scheduled from May 5, 2025 through July 28, 2025 is now anticipated to be completed by Sunday, July 6, 2025. As such, effective Timely Cycle for the Gas Day of Monday, July 7, 2025 and until further notice, Interruptible storage injection services including Authorized Overrun will be scheduled at Thomas Corners Storage (Pin #302015) until further notice.
The Unit 1 Overhaul scheduled to begin at the Steuben Storage Facility on July 7, 2025 and continue through August 8, 2025 will continue on schedule as previously posted. As such, effective Timely Cycle for the Gas Day of Monday, July 7, 2025 and until further notice, Interruptible storage injection services including Authorized Overrun will continue to not be scheduled at Steuben Storage (Pin #303000) until further notice.
Updates will be posted as more information is received.
Please call your Account Manager or Scheduling Representative if you have questions.
Your session will expire in . Click OK to renew your session.