Effective Evening Cycle (9:00) for the gas day of March 13, 2023 Tennessee restricted the following:
OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS
NONE
RESTRICTIONS
· VCP/TGP Valley Crossing Allocation Receipt Meter (Pin 53608) - through approx 99% of SOP increases due to operational concerns; 121,052 Dths
· Net Mexi/TGP Gillrina Road Nueces Receipt Meter (Pin 47799) - through 100% of SOP increases due to operational concerns; 15 Dths
· STA 9 (Segment 109 FH) - through approx 85% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 141,423 Dths
· STA 40 South Of Carthage (Segment 132 FH) - through 100% of SOP increases due to an emergent repair at STA 40; 246,905 Dths
· STA 47 (Segment 143 FH) - through 100% of SA increases due to scheduled maintenance and nominations in excess of operational capacity; 34,959 Dths
· MLV 509 (Segment 509 BH) - through 100% of IT increases due to nominations in excess of operational capacity; 1,195 Dths
· STA 860 (Segment 860 BH) - through 100% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 132,405 Dths
· Transco/TGP Heidelberg Mississippi Delivery Meter (Pin 420291) - through 100% of SIPps increases due to operational concerns; 10 Dths
· MLV 314 East (Segment 314 BH) - through approx 99% of SOP increases due to nominations in excess of operational capacity; 52,974 Dths
· STA 315 (Segment 315 BH) - through approx 62% of SOP increases due to nominations in excess of operational capacity; 86,909 Dths
· STA 321 (Segment 321 FH) - through 100% of SOP increases due nominations in excess of operational capacity and an emergent repair at STA 323; 801,416 Dths
· AGT/TGP Mahwah New Jersey Bergen Delivery Meter (Pin 420207) - through approx 43% of SOP increases due to nominations in excess of operational capacity; 61,183 Dths
· STA 224 (Segment 224 FH) - through approx 83% of SOP increases due to nominations in excess of operational capacity; 108,534 Dths
· Z5HC North (Segment 299 FH) - through 100% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 596,979 Dths
· STA 245 (Segment 245 FH) - through approx 94% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 394,291 Dths
· STA 261 Discharge East (Segment 261 FH) - through 100% of SOP increases due to nominations in excess of operational capacity; 81,282 Dths
· MLV 273 (Segment 284 FH) - through 100% of SOP increases due to nominations in excess of operational capacity; 94,512 Dths
LINEPACK RESTRICTIONS
Payback will be evaluated at each cycle and scheduled only if operationally feasible.
STORAGE RESTRICTIONS
Tennessee will NOT approve any transfers from accounts at TGP Bear Creek Storage to SNG Bear Creek Storage (460017) (IS-PA, FS-PA) until further notice. Transfers into TGP Bear Creek Storage (460017) from SNG Bear Creek Storage will be allowed under the FS-PA storage service only with partner approvals.
**PLEASE NOTE THAT FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.
**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED SERVICE OUTAGES.
If you have any questions, please contact your Scheduler.