Effective Timely Cycle (9:00) for the gas day of March 07, 2023 Tennessee restricted the following:
OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS
OFO DAILY CRITICAL DAY 1 FOR ALL AREAS EAST OF STA 254 ON THE 200 LINE FOR OVER-TAKES FROM THE SYSTEM AND UNDER-DELIVERIES INTO THE SYSTEM FOR ALL BALANCING PARTIES
RESTRICTIONS
· Whistlep/TGP Whistler Receipt Nuece Receipt Meter (Pin 54847) - through 100% of SIPss due to imbalance management quantity exceeded; 10,221 Dths
· STA 834 (Segment 834 BH) - through approx 40% of SOP due to nominations in excess of operational capacity; 92,400 Dths
· STA 860 (Segment 860 BH) - through 100% of SOP due to scheduled maintenance and nominations in excess of operational capacity; 143,172 Dths
· Trnsco/TGP Heidelberg Missisippi Ja Delivery Meter (Pin 420291) - through 100% of SIPps due to operational concerns; 10 Dths
· TGP/SNG Rose Hill Miss Clarke Delivery Meter (Pin 420546) - through approx 44% of SIPps due to nominations in excess of operational capacity; 160,175 Dths
· STA 110 South (Segment 187 BH) - through 100% of SOP due to scheduled maintenance and nominations in excess of operational capacity; 73,047 Dths
· STA 307 (Segment 307 BH) - through 100% of SOP due to force majeure at MLV 309 to MLV 310; 4,191 Dths
· MLV 314 East (Segment 314 BH) - through approx 84% of SOP due to nominations in excess of operational capacity; 237,879 Dths
· STA 315 (Segment 315 BH) - through approx 77% of SOP due to nominations in excess of operational capacity; 426,390 Dths
· STA 321 (Segment 321 FH) - through approx 95% of SOP due to nominations in excess of operational capacity; 969,186 Dths
· Agt/TGP Mahwah New Jersey Bergen Delivery Meter (Pin 420207) - through approx 25% of SIPss due to nominations in excess of operational capacity; 152,877 Dths
· MLV 336 East (Segment 336 FH) - through approx 87% of SOP due to nominations in excess of operational capacity; 50,006 Dths
· MLV 355 (Segment 355 BH) - through 100% of IT due to operational concerns; 24,123 Dths
· STA 224 (Segment 224 FH) - through approx 59% of SOP due to nominations in excess of operational capacity; 201,350 Dths
· Z5HC North (Segment 299 FH) - through approx 95% of SOP due to nominations in excess of operational capacity; 958,420 Dths
· STA 245 (Segment 245 FH) - through approx 97% of SOP due to scheduled maintenance and nominations in excess of operational capacity; 553,771 Dths
· Wright Receipt Meter (Pin 412181) - through approx 83% of SIPss due to nominations in excess of operational capacity; 200,282 Dths
· MLV 256 East (Segment 256 FH) - through approx 48% of SOP due to nominations in excess of operational capacity; 58,603 Dths
· STA 261 Discharge East (Segment 261 FH) - through 100% of SOP due to nominations in excess of operational capacity; 181,098 Dths
· MLV 273 (Segment 284 FH) - through 100% of SOP due to nominations in excess of operational capacity; 124,512 Dths
· STA 268 North(Segment 268 FH) - through 100% of SOP due to nominations in excess of operational capacity; 97 Dths
LINEPACK RESTRICTIONS
Payback will be evaluated at each cycle and scheduled only if operationally feasible.
STORAGE RESTRICTIONS
Tennessee will NOT approve any transfers from accounts at TGP Bear Creek Storage to SNG Bear Creek Storage (460017) (IS-PA, FS-PA) until further notice. Transfers into TGP Bear Creek Storage (460017) from SNG Bear Creek Storage will be allowed under the FS-PA storage service only with partner approvals.
**PLEASE NOTE THAT FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.
**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED SERVICE OUTAGES.
If you have any questions, please contact your Scheduler.