TSP/TSP Name:  1939164-TENNESSEE GAS PIPELINE Critical: Y
Notice Type Desc (1):  PIPELINE CONDITIONS Notice Type Desc (2):  CURRENT PIPELINE CONDITIONS
Notice Eff Date/Time:  02/27/2023 2:13:58PM Notice End Date/Time:  02/28/2023 9:00:00am
Post Date/Time:  2/27/2023 2:13:58 PM Notice ID: 386077
Reqrd Rsp:  1 Rsp Date:  02/27/2023
Notice Stat Desc:  INITIATE Prior Notice: 
Subject:  RESTRICTIONS FOR 02-28-2023 TIMELY CYCLE
Notice Text:

Effective Timely Cycle (9:00) for the gas day of February 28, 2023 Tennessee restricted the following:

OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS

OFO DAILY CRITICAL DAY 1 FOR ALL AREAS EAST OF STA 254 ON THE 200 LINE ONLY FOR OVER-TAKES FROM THE SYSTEM OR UNDER-DELIVERIES INTO THE SYSTEM FOR ALL BALANCING PARTIES

RESTRICTIONS

·         STA 40 South Of Carthage (Segment 132 FH) - through 100% of SA  due to emergent repair at STA 40; 16,637 Dths

·         Trnsco/TGP Kinder La  Exch  (Bi  1 Delivery Meter (Pin 420373) - through 100% of SOP  due to operational concerns; 2,048 Dths

·         STA 834 (Segment 834 BH) - through approx 59% of SOP  due to nominations in excess of operational capacity; 165,107 Dths

·         STA 860 (Segment 860 BH) - through 100% of SOP  due to scheduled maintenance and nominations in excess of operational capacity; 114,956 Dths

·         Trnsco/TGP Heidelberg Missisippi Ja Delivery Meter (Pin 420291) - through 100% of SIPps  due to operational concerns; 10 Dths

·         TGP/SNG Rose Hill Miss Clarke Delivery Meter (Pin 420546) - through approx 45% of SIPps  due to nominations in excess of operational capacity; 163,821 Dths

·         STA 110 South (Segment 187 BH) - through 100% of SOP  due to scheduled maintenance and nominations in excess of operational capacity; 87,212 Dths

·         STA 307 (Segment 307 BH) - through 100% of SOP  due to force majeure at MLV 309 to MLV 310; 36,414 Dths

·         MLV 314 East (Segment 314 BH) - through approx 73% of SOP  due to nominations in excess of operational capacity; 199,368 Dths

·         STA 315 (Segment 315 BH) - through approx 70% of SOP  due to nominations in excess of operational capacity; 362,629 Dths

·         STA 321 (Segment 321 FH) - through approx 89% of SOP  due to nominations in excess of operational capacity; 950,904 Dths

·         Agt/TGP Mahwah New Jersey Bergen Delivery Meter (Pin 420207) - through approx 79% of SOP  due to nominations in excess of operational capacity; 96,647 Dths

·         Trnsco/TGP Rivervale New Jersey Ber Delivery Meter (Pin 420101) - through approx 5% of SOP  due to nominations in excess of operational capacity; 6,149 Dths

·         MLV 336 East (Segment 336 FH) - through approx 99% of SOP  due to nominations in excess of operational capacity; 57,418 Dths

·         MLV 355 (Segment 355 BH) - through 100% of IT  due to operational concerns; 4,372 Dths

·         STA 224 (Segment 224 FH) - through approx 81% of SOP  due to nominations in excess of operational capacity; 267,849 Dths

·         Z5HC North (Segment 299 FH) - through approx 96% of SOP  due to nominations in excess of operational capacity; 956,484 Dths

·         STA 245 (Segment 245 FH) - through 100% of SOP  due to scheduled maintenance and nominations in excess of operational capacity; 568,224 Dths

·         Wright Receipt Meter (Pin 412181) - through approx 28% of SIPsp  due to nominations in excess of operational capacity; 225,129 Dths

·         MLV 256 East (Segment 256 FH) - through approx 90% of SOP  due to nominations in excess of operational capacity; 108,955 Dths

·         STA 261 Discharge East (Segment 261 FH) - through 100% of SOP  due to nominations in excess of operational capacity; 132,812 Dths

·         MLV 273 (Segment 284 FH) - through 100% of SOP  due to nominations in excess of operational capacity; 124,512 Dths

·         STA 268 North(Segment 268 FH) - through 100% of SOP  due to nominations in excess of operational capacity; 2,812 Dths

LINEPACK RESTRICTIONS

Payback will be evaluated at each cycle and scheduled only if operationally feasible.

STORAGE RESTRICTIONS

Tennessee will NOT approve any transfers from accounts at TGP Bear Creek Storage to SNG Bear Creek Storage (460017) (IS-PA, FS-PA) until further notice.  Transfers into TGP Bear Creek Storage (460017) from SNG Bear Creek Storage will be allowed under the FS-PA storage service only with partner approvals.

 

 

 

**PLEASE NOTE THAT FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.

**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED SERVICE OUTAGES.