Effective Evening Cycle (9:00) for the gas day of February 24, 2023 Tennessee restricted the following:
OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS
OFO DAILY CRITICAL DAY 1 FOR ALL AREAS EAST OF STA 245 AND STA 315 FOR OVER-TAKES FROM THE SYSTEM OR UNDER-DELIVERIES INTO THE SYSTEM FOR ALL BALANCING PARTIES
RESTRICTIONS
· STA 40 South Of Carthage (Segment 132 FH) - through 100% of SOP increases due to emergent repair at STA 40; 211,659 Dths
· MLV 509 (Segment 509 BH) - through 100% of SOP increases due to nominations in excess of operational capacity; 12,248 Dths
· STA 823 (Segment 823 BH) - through approx 91% of SOP increases due to nominations in excess of operational capacity; 8,855 Dths
· STA 834 (Segment 834 BH) - through approx 98% of SOP increases due to nominations in excess of operational capacity; 146,788 Dths
· Trnsco/TGP Heidelberg Missisippi Ja Delivery Meter (Pin 420291) - through 100% of SIPps increases due to operational concerns; 10 Dths
· STA 110 South (Segment 187 BH) - through 100% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 38,830 Dths
· STA 307 (Segment 307 BH) - through 100% of SOP increases due to force majeure at MLV 309 to MLV 310; 36,414 Dths
· MLV 314 East (Segment 314 BH) - through approx 67% of SOP increases due to nominations in excess of operational capacity; 91,987 Dths
· STA 321 (Segment 321 FH) - through approx 99% of SOP increases due to nominations in excess of operational capacity; 543,383 Dths
· STA 224 (Segment 224 FH) - through approx 96% of SOP increases due to nominations in excess of operational capacity; 159,270 Dths
· Z5HC North (Segment 299 FH) - through approx 99% of SOP increases due to nominations in excess of operational capacity; 263,055 Dths
· STA 245 (Segment 245 FH) - through 100% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 238,366 Dths
· Wright Receipt Meter (Pin 412181) - through approx 91% of SIPss increases due to nominations in excess of operational capacity; 172,736 Dths
· MLV 256 East (Segment 256 FH) - through approx 94% of SOP increases due to nominations in excess of operational capacity; 107,907 Dths
· MLV 273 (Segment 284 FH) - through 100% of SOP increases due to nominations in excess of operational capacity; 97,765 Dths
· STA 268 North(Segment 268 FH) - through 100% of SOP increases due to nominations in excess of operational capacity; 2,776 Dths
LINEPACK RESTRICTIONS
Payback will be evaluated at each cycle and scheduled only if operationally feasible.
STORAGE RESTRICTIONS
Tennessee will NOT approve any transfers from accounts at TGP Bear Creek Storage to SNG Bear Creek Storage (460017) (IS-PA, FS-PA) until further notice. Transfers into TGP Bear Creek Storage (460017) from SNG Bear Creek Storage will be allowed under the FS-PA storage service only with partner approvals.
**PLEASE NOTE THAT FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.
**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED SERVICE OUTAGES.
If you have any questions, please contact your Scheduler.