Effective Timely Cycle (9:00) for the gas day of February 08, 2023 Tennessee restricted the following:
OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS
NONE
RESTRICTIONS
· Whistlep/TGP Whistler Receipt Nuece Receipt Meter (Pin 54847) - through 100% of SIPsp due to imbalance management; 22,821 Dths
· STA 9 (Segment 109 FH) - through approx 41% of SA due to an Emergent Repair issue between MLV 11 and MLV 12; 49,830 Dths
· Trnsco/TGP Kinder La Exch (Bi 1 Delivery Meter (Pin 420373) - through 100% of SOP due to operational concerns; 2,048 Dths
· Pine Pra/TGP Pine Prairie North Rap Delivery Meter (Pin 421043) - through approx 6% of SOP due to operational concerns; 8,208 Dths
· STA 834 (Segment 834 BH) - through approx 64% of SOP due to nominations in excess of operational capacity; 172,007 Dths
· Trnsco/TGP Heidelberg Missisippi Ja Delivery Meter (Pin 420291) - through 100% of SIPps due to operational concerns; 10 Dths
· TGP/SNG Rose Hill Miss Clarke Delivery Meter (Pin 420546) - through approx 51% of SIPps due to nominations in excess of operational capacity; 205,307 Dths
· STA 307 (Segment 307 BH) - through 100% of SOP due to force majeure at MLV 309 to MLV 310; 6,295 Dths
· MLV 314 East (Segment 314 BH) - through approx 47% of SOP due to nominations in excess of operational capacity; 144,968 Dths
· STA 315 (Segment 315 BH) - through approx 47% of SOP due to nominations in excess of operational capacity; 244,442 Dths
· STA 321 (Segment 321 FH) - through approx 83% of SOP due to nominations in excess of operational capacity; 912,205 Dths
· Agt/TGP Mahwah New Jersey Bergen Delivery Meter (Pin 420207) - through approx 72% of SOP due to nominations in excess of operational capacity; 84,231 Dths
· MLV 336 East (Segment 336 FH) - through approx 88% of SOP due to nominations in excess of operational capacity; 95,979 Dths
· MLV 355 (Segment 355 BH) - through 100% of IT due to operational concerns; 38,966 Dths
· STA 224 (Segment 224 FH) - through approx 69% of SOP due to nominations in excess of operational capacity; 234,801 Dths
· Z5HC North (Segment 299 FH) - through approx 93% of SOP due to nominations in excess of operational capacity; 918,274 Dths
· STA 245 (Segment 245 FH) - through approx 94% of SOP due to scheduled maintenance and nominations in excess of operational capacity; 433,353 Dths
· Wright Receipt Meter (Pin 412181) - through approx 24% of SIPss due to nominations in excess of operational capacity; 138,798 Dths
· MLV 256 East (Segment 256 FH) - through approx 43% of SOP due to scheduled maintenance and nominations in excess of operational capacity; 83,989 Dths
· STA 261 Discharge East (Segment 261 FH) - through approx 61% of SOP due to nominations in excess of operational capacity; 92,854 Dths
· MLV 273 (Segment 284 FH) - through 100% of SOP due to nominations in excess of operational capacity; 124,581 Dths
LINEPACK RESTRICTIONS
Payback will be evaluated at each cycle and scheduled only if operationally feasible.
STORAGE RESTRICTIONS
Tennessee will NOT approve any transfers from accounts at TGP Bear Creek Storage to SNG Bear Creek Storage (460017) (IS-PA, FS-PA) until further notice. Transfers into TGP Bear Creek Storage (460017) from SNG Bear Creek Storage will be allowed under the FS-PA storage service only with partner approvals.
**PLEASE NOTE THAT FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.
**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED SERVICE OUTAGES.
If you have any questions, please contact your Scheduler.