Effective Intraday 1 Cycle (14:00) for the gas day of February 03, 2023 Tennessee restricted the following:
OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS
OFO DAILY CRITICAL DAY 1 FOR ALL OF ZONES L, 1, 2, 3, 4, 5 AND 6 FOR UNDER-DELIVERIES INTO THE SYSTEM AND OVER-TAKES FROM THE SYSTEM FOR ALL BALANCING PARTIES
RESTRICTIONS
· Cproc/TGP Hcp Colorado Receipt Meter (Pin 410144) - through approx 60% of SA increases due to operational concerns; 189 Dths
· TGP/PHP Sheridan Colorado Receipt Meter (Pin 54086) - through approx 60% of SA increases due to operational concerns; 7,474 Dths
· STA 40 South of Carthage (Segment 132 FH) - through approx 20% of SA increases due to nominations in excess of operational capacity; 37,089 Dths
· Transco/TGP Heidelberg Mississippi Delivery Meter (Pin 420291) - through 100% of SIPps increases due to operational concerns; 10 Dths
· STA 307 (Segment 307 BH) - through 100% of SOP increases due to FMJ at MLV 309 to MLV 310; 36,414 Dths
· STA 321 (Segment 321 FH) - through 100% of SOP increases due to nominations in excess of operational capacity; 927,930 Dths
· Transco/TGP Rivervale New Jersey Delivery Meter (Pin 420101) - through approx 13% of SOP increases due to nominations in excess of operational capacity; 6,149 Dths
· MLV 336 East (Segment 336 FH) - through 100% of SOP increases due to nominations in excess of operational capacity; 4,946 Dths
· STA 224 (Segment 224 FH) - through 100% of SOP increases due to nominations in excess of operational capacity; 221,751 Dths
· Z5HC North (Segment 299 FH) - through 100% of SOP increases due to nominations in excess of operational capacity; 570,736 Dths
· STA 245 (Segment 245 FH) - through 100% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 268,366 Dths
· Wright Receipt Meter (Pin 412181) - through approx 17% of SIPss increases due to nominations in excess of operational capacity; 15,320 Dths
· MLV 256 East (Segment 256 FH) - through approx 57% of SOP increases due to nominations in excess of operational capacity; 60,153 Dths
· MLV 260A-North Hampton Lateral (Segment 280 FH) - through 100% of SOP increases due to nominations in excess of operational capacity; 6,530 Dths
· MLV 273 (Segment 284 FH) - through 100% of SOP increases due to nominations in excess of operational capacity; 74,512 Dths
· STA 268 North(Segment 268 FH) - through 100% of SOP increases due to nominations in excess of operational capacity; 98 Dths
LINEPACK RESTRICTIONS
Payback will be evaluated at each cycle and scheduled only if operationally feasible.
STORAGE RESTRICTIONS
Nominations for Interruptible Storage Withdrawal Services under Rate Schedule IS (IS-MA) at the Northern MA (460018) storage field and nominations for Interruptible Storage Withdrawal Services under Rate Schedule IS (IS-PA) at the Bear Creek PA (460017) storage field will not be allowed until further notice. Tennessee will NOT approve any transfers from accounts at TGP Bear Creek Storage to SNG Bear Creek Storage (460017) (IS-PA, FS-PA) until further notice. Transfers into TGP Bear Creek Storage (460017) from SNG Bear Creek Storage will be allowed under the FS-PA storage service only with partner approvals.
**PLEASE NOTE THAT FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.
**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED SERVICE OUTAGES.
If you have any questions, please contact your Scheduler.