Effective Intraday 2 Cycle (18:00) for the gas day of February 01, 2023 Tennessee restricted the following:
OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS
OFO DAILY CRITICAL DAY 1 FOR ALL OF ZONES 4, 5 AND 6 FOR UNDER-DELIVERIES INTO THE SYSTEM AND OVER-TAKES FROM THE SYSTEM FOR ALL BALANCING PARTIES
RESTRICTIONS
· MLV 509 (Segment 509 BH) - through 100% of IT increases due to nominations in excess of operational capacity; 26,700 Dths
· Pine Pra/TGP Pine Prairie North Rap Delivery Meter (Pin 421043) - through approx 90% of SOP increases due to operational concerns; 9,544 Dths
· Trnsco/TGP Heidelberg Missisippi Ja Delivery Meter (Pin 420291) - through 100% of SIPps increases due to operational concerns; 10 Dths
· STA 307 (Segment 307 BH) - through 100% of SOP increases due to FMJ at MLV 309 to MLV 310; 17,674 Dths
· MLV 314 East (Segment 314 BH) - through approx 90% of SOP increases due to nominations in excess of operational capacity; 41,484 Dths
· STA 315 (Segment 315 BH) - through approx 35% of SOP increases due to nominations in excess of operational capacity; 24,474 Dths
· STA 321 (Segment 321 FH) - through approx 97% of SOP increases due to nominations in excess of operational capacity; 375,015 Dths
· Trnsco/TGP Rivervale New Jersey Ber Delivery Meter (Pin 420101) - through approx 13% of SOP increases due to nominations in excess of operational capacity; 6,149 Dths
· MLV 336 East (Segment 336 FH) - through approx 98% of SOP increases due to nominations in excess of operational capacity; 51,050 Dths
· STA 224 (Segment 224 FH) - through approx 21% of SOP increases due to nominations in excess of operational capacity; 15,000 Dths
· Z5HC North (Segment 299 FH) - through approx 99% of SOP increases due to nominations in excess of operational capacity; 249,733 Dths
· STA 245 (Segment 245 FH) - through 100% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 243,366 Dths
· MLV 256 East (Segment 256 FH) - through 100% of SOP increases due to nominations in excess of operational capacity; 35,187 Dths
· MLV 273 (Segment 284 FH) - through 100% of SOP increases due to nominations in excess of operational capacity; 49,872 Dths
LINEPACK RESTRICTIONS
Payback will be evaluated at each cycle and scheduled only if operationally feasible.
STORAGE RESTRICTIONS
Tennessee will NOT approve any transfers from accounts at TGP Bear Creek Storage to SNG Bear Creek Storage (460017)(IS-PA, FS-PA) until further notice. Transfers into TGP Bear Creek Storage (460017) from SNG Bear Creek Storage will be allowed under the FS-PA storage service only with partner approvals.
**PLEASE NOTE THAT FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.
**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED SERVICE OUTAGES.