Effective Intraday 1 Cycle (14:00) for the gas day of January 30, 2023 Tennessee restricted the following:
OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS
OFO DAILY CRITICAL DAY 1 FOR ZONE 4 300 LEG LMS-PAS ONLY FOR UNDER-DELIVERIES INTO THE SYSTEM
RESTRICTIONS
· MLV 509 (Segment 509 BH) - through 100% of IT increases due to nominations in excess of operational capacity; 30,868 Dths
· Pine Pra/TGP Pine Prairie North Rap Delivery Meter (Pin 421043) - through approx 89% of SOP increases due to operational concerns; 104,149 Dths
· STA 834 (Segment 834 BH) - through 100% of SOP increases due to nominations in excess of operational capacity; 7,499 Dths
· Gulfsth/TGP Petal Storage Field For Delivery Meter (Pin 420797) - through approx 14% of SOP increases due to operational concerns; 3,937 Dths
· Trnsco/TGP Heidelberg Missisippi Ja Delivery Meter (Pin 420291) - through 100% of SIPps increases due to operational concerns; 10 Dths
· STA 307 (Segment 307 BH) - through 100% of SOP increases due to force majeure at MLV 309 to MLV 310; 25,000 Dths
· MLV 314 East (Segment 314 BH) - through approx 72% of SOP increases due to nominations in excess of operational capacity; 59,172 Dths
· STA 315 (Segment 315 BH) - through approx 11% of SOP increases due to nominations in excess of operational capacity; 9,599 Dths
· Debm/TGP Beirne Hill Sales Bradford Delivery Meter (Pin 48061) - through approx 94% of IT increases due to nominations in excess of operational capacity; 8,016 Dths
· STA 321 (Segment 321 FH) - through approx 99% of SOP increases due to nominations in excess of operational capacity; 346,403 Dths
· Agt/TGP Mahwah New Jersey Bergen Delivery Meter (Pin 420207) - through approx 4% of IT increases due to nominations in excess of operational capacity; 736 Dths
· MLV 336 East (Segment 336 FH) - through 100% of SOP increases due to nominations in excess of operational capacity; 50,386 Dths
· Z5HC North (Segment 299 FH) - through approx 99% of SOP increases due to nominations in excess of operational capacity; 376,492 Dths
· STA 245 (Segment 245 FH) - through 100% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 257,440 Dths
· STA 261 Discharge East (Segment 261 FH) - through approx 79% of SOP increases due to nominations in excess of operational capacity; 20,526 Dths
· MLV 273 (Segment 284 FH) - through 100% of SOP increases due to nominations in excess of operational capacity; 54,512 Dths
LINEPACK RESTRICTIONS
Payback will be evaluated at each cycle and scheduled only if operationally feasible.
STORAGE RESTRICTIONS
Tennessee will NOT approve any transfers from accounts at TGP Bear Creek Storage to SNG Bear Creek Storage (460017)(IS-PA, FS-PA) until further notice. Transfers into TGP Bear Creek Storage (460017) from SNG Bear Creek Storage will be allowed under the FS-PA storage service only with partner approvals.
**PLEASE NOTE THAT FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.
**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED SERVICE OUTAGES.
If you have any questions, please contact your Scheduler.