Effective Evening Cycle (9:00) for the gas day of January 25, 2023 Tennessee restricted the following:
OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS
NONE
RESTRICTIONS
· Pine Pra/TGP Pine Prairie North Rap Delivery Meter (Pin 421043) - through approx 33% of SOP increases due to operational concerns; 34,571 Dths
· STA 834 (Segment 834 BH) - through approx 90% of SOP increases due to nominations in excess of operational capacity; 122,127 Dths
· Trnsco/TGP Heidelberg Missisippi Ja Delivery Meter (Pin 420291) - through 100% of SIPps increases due to operational concerns; 10 Dths
· MLV 539 (Segment 534 BH) - through 100% of SOP increases due to emergent repair at MLV 538-1 to 539-1; 142,577 Dths
· MLV 314 East (Segment 314 BH) - through approx 89% of SOP increases due to nominations in excess of operational capacity; 128,846 Dths
· Debm/TGP Beirne Hill Sales Bradford Delivery Meter (Pin 48061) - through approx 25% of IT increases due to nominations in excess of operational capacity; 2,145 Dths
· STA 321 (Segment 321 FH) - through approx 99% of SOP increases due to nominations in excess of operational capacity; 515,522 Dths
· Agt/TGP Mahwah New Jersey Bergen Delivery Meter (Pin 420207) - through approx 72% of SOP increases due to nominations in excess of operational capacity; 115,929 Dths
· MLV 336 East (Segment 336 FH) - through approx 97% of SOP increases due to nominations in excess of operational capacity; 50,537 Dths
· MLV 355 (Segment 355 BH) - through 100% of IT increases due to operational concerns; 25,584 Dths
· Z5HC North (Segment 299 FH) - through approx 99% of SOP increases due to nominations in excess of operational capacity; 352,870 Dths
· STA 245 (Segment 245 FH) - through 100% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 251,657 Dths
· Wright Receipt Meter (Pin 412181) - through approx 62% of SOP increases due to nominations in excess of operational capacity; 61,418 Dths
· MLV 256 East (Segment 256 FH) - through approx 44% of SOP increases due to nominations in excess of operational capacity; 40,642 Dths
· STA 261 Discharge East (Segment 261 FH) - through approx 77% of SOP increases due to nominations in excess of operational capacity; 59,025 Dths
· MLV 273 (Segment 284 FH) - through 100% of SOP increases due to nominations in excess of operational capacity; 94,581 Dths
LINEPACK RESTRICTIONS
Payback will be evaluated at each cycle and scheduled only if operationally feasible.
STORAGE RESTRICTIONS
Tennessee will NOT approve any transfers from accounts at TGP Bear Creek Storage to SNG Bear Creek Storage (460017)(IS-PA, FS-PA) until further notice. Transfers into TGP Bear Creek Storage (460017) from SNG Bear Creek Storage will be allowed under the FS-PA storage service only with partner approvals.
**PLEASE NOTE THAT FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.
**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED SERVICE OUTAGES.
If you have any questions, please contact your Scheduler.