Effective Timely Cycle (9:00) for the gas day of January 24, 2023 Tennessee restricted the following:
OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS
NONE
RESTRICTIONS
· Pine Pra/TGP Pine Prairie North Rap Delivery Meter (Pin 421043) - through approx 41% of SOP due to operational concerns; 81,039 Dths
· STA 834 (Segment 834 BH) - through approx 64% of SOP due to nominations in excess of operational capacity; 164,950 Dths
· Trnsco/TGP Heidelberg Missisippi Ja Delivery Meter (Pin 420291) - through 100% of SIPps due to operational concerns; 10 Dths
· TGP/SNG Rose Hill Miss Clarke Delivery Meter (Pin 420546) - through approx 48% of SIPps due to nominations in excess of operational capacity; 184,131 Dths
· MLV 314 East (Segment 314 BH) - through approx 93% of SOP due to nominations in excess of operational capacity; 247,612 Dths
· STA 315 (Segment 315 BH) - through approx 74% of SOP due to nominations in excess of operational capacity; 382,223 Dths
· STA 321 (Segment 321 FH) - through approx 89% of SOP due to nominations in excess of operational capacity; 959,920 Dths
· Agt/TGP Mahwah New Jersey Bergen Delivery Meter (Pin 420207) - through approx 99% of SOP due to nominations in excess of operational capacity; 172,717 Dths
· MLV 336 East (Segment 336 FH) - through approx 96% of SOP due to nominations in excess of operational capacity; 104,918 Dths
· MLV 355 (Segment 355 BH) - through 100% of IT due to operational concerns; 27,738 Dths
· Z5HC North (Segment 299 FH) - through approx 97% of SOP due to nominations in excess of operational capacity; 947,709 Dths
· STA 245 (Segment 245 FH) - through 100% of SOP due to scheduled maintenance and nominations in excess of operational capacity; 577,133 Dths
· Wright Receipt Meter (Pin 412181) - through approx 57% of SIPss due to nominations in excess of operational capacity; 150,579 Dths
· MLV 256 East (Segment 256 FH) - through approx 59% of SOP due to nominations in excess of operational capacity; 101,871 Dths
· STA 261 Discharge East (Segment 261 FH) - through approx 74% of SOP due to nominations in excess of operational capacity; 82,587 Dths
· MLV 273 (Segment 284 FH) - through 100% of SOP due to nominations in excess of operational capacity; 146,468 Dths
LINEPACK RESTRICTIONS
Payback will be evaluated at each cycle and scheduled only if operationally feasible.
STORAGE RESTRICTIONS
Tennessee will NOT approve any transfers from accounts at TGP Bear Creek Storage to SNG Bear Creek Storage (460017)(IS-PA, FS-PA) until further notice. Transfers into TGP Bear Creek Storage (460017) from SNG Bear Creek Storage will be allowed under the FS-PA storage service only with partner approvals.
**PLEASE NOTE THAT FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.
**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED SERVICE OUTAGES.
If you have any questions, please contact your Scheduler.