Effective Timely Cycle (9:00) for the gas day of January 13, 2023 Tennessee restricted the following:
OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS
NONE
RESTRICTIONS
· Whistlep/TGP Whistler Receipt Nuece Receipt Meter (Pin 54847) - through 100% of SIPsp due to imbalance management; 70,521 Dths
· Etc Tig/TGP Chatham Jackson Receipt Meter (Pin 412830) - through 100% of IT deliveries due to displacement gas unavailable for backhaul; 59,840 Dths
· Pine Pra/TGP Pine Prairie North Rap Delivery Meter (Pin 421043) - through approx 24% of SOP due to operational concerns; 36,849 Dths
· STA 834 (Segment 834 BH) - through approx 64% of SOP due to nominations in excess of operational capacity; 163,262 Dths
· Trnsco/TGP Heidelberg Missisippi Ja Delivery Meter (Pin 420291) - through 100% of SIPps due to operational concerns; 10 Dths
· TGP/SNG Rose Hill Miss Clarke Delivery Meter (Pin 420546) - through approx 49% of SIPps due to nominations in excess of operational capacity; 191,646 Dths
· MLV 314 East (Segment 314 BH) - through approx 92% of SOP due to nominations in excess of operational capacity; 239,532 Dths
· STA 315 (Segment 315 BH) - through approx 80% of SOP due to nominations in excess of operational capacity; 410,978 Dths
· STA 321 (Segment 321 FH) - through approx 87% of SOP due to nominations in excess of operational capacity; 789,637 Dths
· Agt/TGP Mahwah New Jersey Bergen Delivery Meter (Pin 420207) - through approx 5% of SIPss due to nominations in excess of operational capacity; 202,004 Dths
· MLV 336 East (Segment 336 FH) - through approx 96% of SOP due to nominations in excess of operational capacity; 111,701 Dths
· MLV 355 (Segment 355 BH) - through 100% of IT due to operational concerns; 73,290 Dths
· Z5HC North (Segment 299 FH) - through approx 92% of SOP due to nominations in excess of operational capacity; 864,313 Dths
· STA 245 (Segment 245 FH) - through approx 95% of SOP due to scheduled maintenance and nominations in excess of operational capacity; 712,845 Dths
· Wright Receipt Meter (Pin 412181) - through approx 61% of SOP due to nominations in excess of operational capacity; 163,498 Dths
· STA 261 Discharge East (Segment 261 FH) - through approx 19% of SOP due to nominations in excess of operational capacity; 36,746 Dths
· MLV 273 (Segment 284 FH) - through 100% of SOP due to nominations in excess of operational capacity; 101,198 Dths
LINEPACK RESTRICTIONS
Payback will be evaluated at each cycle and scheduled only if operationally feasible.
STORAGE RESTRICTIONS
Tennessee will NOT approve any transfers from accounts at TGP Bear Creek Storage to SNG Bear Creek Storage (460017)(IS-PA, FS-PA) until further notice. Transfers into TGP Bear Creek Storage (460017) from SNG Bear Creek Storage will be allowed under the FS-PA storage service only with partner approvals.
**PLEASE NOTE THAT FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.
**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED SERVICE OUTAGES.
If you have any questions, please contact your Scheduler.