Effective Evening Cycle (9:00) for the gas day of January 07, 2023 Tennessee restricted the following:
OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS
NONE
RESTRICTIONS
· Pine Pra/TGP Pine Prairie North Rap Delivery Meter (Pin 421043) - through approx 33% of SOP increases due to operational concerns; 35,861 Dths
· STA 834 (Segment 834 BH) - through 100% of SOP increases due to nominations in excess of operational capacity; 226,857 Dths
· Gulfsth/TGP Petal Storage Field For Delivery Meter (Pin 420797) - through approx 13% of SIPps increases due to operational concerns; 4,926 Dths
· Trnsco/TGP Heidelberg Missisippi Ja Delivery Meter (Pin 420291) - through 100% of SIPps increases due to operational concerns; 10 Dths
· TGP/SNG Rose Hill Miss Clarke Delivery Meter (Pin 420546) - through approx 53% of SIPps increases due to nominations in excess of operational capacity; 15,342 Dths
· MLV 548 (Segment 542 BH) - through approx 18% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 7,486 Dths
· MLV 314 East (Segment 314 BH) - through approx 94% of SOP increases due to nominations in excess of operational capacity; 139,126 Dths
· STA 315 (Segment 315 BH) - through approx 63% of SOP increases due to nominations in excess of operational capacity; 92,648 Dths
· STA 321 (Segment 321 FH) - through approx 95% of SOP increases due to nominations in excess of operational capacity; 439,925 Dths
· Agt/TGP Mahwah New Jersey Bergen Delivery Meter (Pin 420207) - through approx 69% of SOP increases due to nominations in excess of operational capacity; 146,364 Dths
· MLV 355 (Segment 355 BH) - through 100% of IT increases due to operational concerns; 39,929 Dths
· Z5HC North (Segment 299 FH) - through approx 99% of SOP increases due to nominations in excess of operational capacity; 554,516 Dths
· STA 245 (Segment 245 FH) - through approx 99% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 240,644 Dths
· Wright Receipt Meter (Pin 412181) - through approx 34% of SIPss increases due to nominations in excess of operational capacity; 63,612 Dths
· MLV 256 East (Segment 256 FH) - through approx 83% of SOP increases due to nominations in excess of operational capacity; 152,592 Dths
· STA 261 Discharge East (Segment 261 FH) - through approx 76% of SOP increases due to nominations in excess of operational capacity; 45,296 Dths
· MLV 273 (Segment 284 FH) - through 100% of SOP increases due to nominations in excess of operational capacity; 105,512 Dths
LINEPACK RESTRICTIONS
Payback will be evaluated at each cycle and scheduled only if operationally feasible.
STORAGE RESTRICTIONS
Tennessee will NOT approve any transfers from accounts at TGP Bear Creek Storage to SNG Bear Creek Storage (460017)(IS-PA, FS-PA) until further notice. Transfers into TGP Bear Creek Storage (460017) from SNG Bear Creek Storage will be allowed under the FS-PA storage service only with partner approvals.
**PLEASE NOTE THAT FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.
**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED SERVICE OUTAGES.
If you have any questions, please contact your Scheduler.