REVISED
Effective Timely Cycle (9:00) for the gas day of January 06, 2023 Tennessee restricted the following:
OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS
NONE
RESTRICTIONS
· Whistlep/TGP Whistler Receipt Nuece Receipt Meter (Pin 54847) - through 100% of SIP due to imbalance management quantity exceeded; 20,001 Dths
· MLV 707 East - Carthage Lateral (Segment 700 FH) - through approx 13% of SA due to nominations in excess of operational capacity; 19,914 Dths
· Pine Pra/TGP Pine Prairie North Rap Delivery Meter (Pin 421043) - through approx 45% of SOP due to operational concerns; 92,427 Dths
· STA 834 (Segment 834 BH) - through approx 67% of SOP due to nominations in excess of operational capacity; 198,700 Dths
· Trnsco/TGP Heidelberg Missisippi Ja Delivery Meter (Pin 420291) - through 100% of SIPps due to operational concerns; 10 Dths
· TGP/SNG Rose Hill Miss Clarke Delivery Meter (Pin 420546) - through approx 37% of SIPps due to nominations in excess of operational capacity; 116,916 Dths
· MLV 314 East (Segment 314 BH) - through approx 94% of SOP due to nominations in excess of operational capacity; 241,080 Dths
· STA 315 (Segment 315 BH) - through approx 82% of SOP due to nominations in excess of operational capacity; 441,616 Dths
· Debm/TGP Beirne Hill Sales Bradford Delivery Meter (Pin 48061) - through approx 1% of SOP due to nominations in excess of operational capacity; 10,296 Dths
· STA 321 (Segment 321 FH) - through approx 83% of SOP due to nominations in excess of operational capacity; 763,206 Dths
· Agt/TGP Mahwah New Jersey Bergen Delivery Meter (Pin 420207) - through approx 92% of SOP due to nominations in excess of operational capacity; 184,614 Dths
· MLV 336 East (Segment 336 FH) - through approx 25% of SOP due to nominations in excess of operational capacity; 4,589 Dths
· MLV 355 (Segment 355 BH) - through 100% of IT due to operational concerns; 51,006 Dths
· Z5HC North (Segment 299 FH) - through approx 92% of SOP due to nominations in excess of operational capacity; 908,938 Dths
· STA 245 (Segment 245 FH) - through approx 93% of SOP due to scheduled maintenance and nominations in excess of operational capacity; 534,909 Dths
· Wright Receipt Meter (Pin 412181) - through approx 92% of SOP due to nominations in excess of operational capacity; 116,633 Dths
· MLV 256 East (Segment 256 FH) - through approx 22% of SOP due to nominations in excess of operational capacity; 57,180 Dths
· STA 261 Discharge East (Segment 261 FH) - through approx 54% of SOP due to nominations in excess of operational capacity; 74,877 Dths
· MLV 273 (Segment 284 FH) - through 100% of SOP due to nominations in excess of operational capacity; 165,615 Dths
LINEPACK RESTRICTIONS
Payback will be evaluated at each cycle and scheduled only if operationally feasible.
STORAGE RESTRICTIONS
Tennessee will NOT approve any transfers from accounts at TGP Bear Creek Storage to SNG Bear Creek Storage (460017)(IS-PA, FS-PA) until further notice. Transfers into TGP Bear Creek Storage (460017) from SNG Bear Creek Storage will be allowed under the FS-PA storage service only with partner approvals.
**PLEASE NOTE THAT FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.
**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED SERVICE OUTAGES.
If you have any questions, please contact your Scheduler.