Effective Evening Cycle (9:00) for the gas day of December 25, 2022 Tennessee restricted the following:
OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS
OFO DAILY BALANCING ALERT FOR ALL OF ZONE 4 FOR OVER-TAKES OUT OF THE SYSTEM OR UNDER-DELIVERIES INTO THE SYSTEM FOR ALL BALANCING PARTIES
OFO DAILY CRITICAL DAY 1 FOR ALL OF ZONES 0, L, 1 AND 2 FOR OVER-TAKES OUT OF THE SYSTEM OR UNDER-DELIVERIES INTO THE SYSTEM FOR LMPAS, SAs ACTING AS BALANCING PARTIES, AND LMMAS
OFO DAILY CRITICAL DAY 1 FOR ALL OF ZONES 3, 4, 5 AND 6 FOR OVER-TAKES OUT OF THE SYSTEM OR UNDER-DELIVERIES INTO THE SYSTEM FOR ALL BALANCING PARTIES
RESTRICTIONS
· STA 47 (Segment 143 FH) - through approx 87% of SOP increases due to nominations in excess of operational capacity; 271,122 Dths
· ETNG/TGP East Lobelville TN Perry Delivery Meter (Pin 420042) - through 100% of SOP increases due to operational concerns; 25,358 Dths
· Pine Prairie /TGP Pine Prairie North Rap Delivery Meter (Pin 421043) - through approx 99% of SOP increases due to operational concerns; 142,619 Dths
· Greenbrier TN 2 (Dual) Delivery Meter (Pin 420289) - through 100% of SOP increases due to operational concerns; 38,533 Dths
· Transco/TGP Heidelberg Mississippi Delivery Meter (Pin 420291) - through 100% of SIPps increases due to operational concerns; 10 Dths
· Tet/TGP Dry Creek Sales Casey Delivery Meter (Pin 420886) - through 100% of SIPps increases due to operational concerns; 44,277 Dths
· Tet/TGP Hanging Rock Scioto Delivery Meter (Pin 421018) - through 100% of SIPps increases due to operational concerns; 195,073 Dths
· STA 315 (Segment 315 BH) - through approx 68% of SOP increases due to nominations in excess of operational capacity; 52,845 Dths
· Debm/TGP Beirne Hill Sales Bradford Delivery Meter (Pin 48061) - through 100% of IT increases due to nominations in excess of operational capacity; 24,356 Dths
· STA 321 (Segment 321 FH) - through 100% of SOP increases due to nominations in excess of operational capacity; 745,525 Dths
· AGT/TGP Mahwah New Jersey Bergen Delivery Meter (Pin 420207) - through 100% of SOP increases due to operational concerns; 239,527 Dths
· Z5HC North (Segment 299 FH) - through approx 99% of SOP increases due to nominations in excess of operational capacity; 536,308 Dths
· STA 245 (Segment 245 FH) - through 100% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 205,741 Dths
· Wright Receipt Meter (Pin 412181) - through approx 77% of SIPss increases due to nominations in excess of operational capacity; 113,740 Dths
· MLV 256 East (Segment 256 FH) - through approx 88% of SOP increases due to nominations in excess of operational capacity; 84,962 Dths
· MLV 273 (Segment 284 FH) - through approx 92% of SOP increases due to nominations in excess of operational capacity; 37,498 Dths
· STA 268 North(Segment 268 FH) - through 100% of SOP increases due to nominations in excess of operational capacity; 2,823 Dths
LINEPACK RESTRICTIONS
Payback OFF the pipe will not be scheduled SYSTEM WIDE.
STORAGE RESTRICTIONS
Tennessee will NOT approve any transfers from accounts at TGP Bear Creek Storage to SNG Bear Creek Storage (460017) (IS-PA, FS-PA) until further notice. Transfers into TGP Bear Creek Storage (460017) from SNG Bear Creek Storage will be allowed under the FS-PA storage service only with partner approvals.
**PLEASE NOTE THAT FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.
**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED SERVICE OUTAGES.
If you have any questions, please contact your Scheduler.