Effective Evening Cycle (9:00) for the gas day of December 21, 2022 Tennessee restricted the following:
OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS
OFO DAILY CRITICAL DAY 1 FOR ALL AREAS EAST OF STA 325 ON THE 300 LINE ONLY FOR OVER-TAKES OUT OF THE SYSTEM OR UNDER-DELIVERIES INTO THE SYSTEM FOR ALL BALANCING PARTIES
RESTRICTIONS
· MLV 707 East - Carthage Lateral (Segment 700 FH) - through approx 48% of SA increases due to nominations in excess of operational capacity; 6,657 Dths
· Pine Prairie /TGP Pine Prairie North Rap Delivery Meter (Pin 421043) - through approx 8% of SOP increases due to operational concerns; 7,577 Dths
· STA 834 (Segment 834 BH) - through approx 68% of SOP increases due to nominations in excess of operational capacity; 60,037 Dths
· Transco/TGP Heidelberg Mississippi Delivery Meter (Pin 420291) - through 100% of SIPps increases due to operational concerns; 10 Dths
· TGP/SNG Rose Hill Miss Clarke Delivery Meter (Pin 420546) - through approx 74% of SIPps increases due to nominations in excess of operational capacity; 77,836 Dths
· MLV 314 East (Segment 314 BH) - through approx 24% of SOP increases due to nominations in excess of operational capacity; 9,841 Dths
· STA 315 (Segment 315 BH) - through approx 72% of SOP increases due to nominations in excess of operational capacity; 164,266 Dths
· STA 321 (Segment 321 FH) - through approx 93% of SOP increases due to nominations in excess of operational capacity; 516,127 Dths
· STA 325 (Segment 324 FH) - through 100% of PIP increases due to the force majeure between STA 325 to MLV 329; 79,914 Dths
· MLV 336 East (Segment 336 FH) - through approx 97% of SOP increases due to nominations in excess of operational capacity; 7,275 Dths
· Z5HC North (Segment 299 FH) - through approx 99% of SOP increases due to nominations in excess of operational capacity; 519,511 Dths
· STA 245 (Segment 245 FH) - through 100% of SIPsp increases due to scheduled maintenance and nominations in excess of operational capacity; 205,918 Dths
· Wright Receipt Meter (Pin 412181) - through approx 89% of SIPss increases due to nominations in excess of operational capacity; 198,476 Dths
· MLV 256 East (Segment 256 FH) - through approx 67% of SOP increases due to nominations in excess of operational capacity; 42,737 Dths
· STA 261 Discharge East (Segment 261 FH) - through approx 61% of SOP increases due to nominations in excess of operational capacity; 20,368 Dths
· MLV 273 (Segment 284 FH) - through approx 99% of SOP increases due to nominations in excess of operational capacity; 72,750 Dths
· STA 268 North(Segment 268 FH) - through 100% of SOP increases due to nominations in excess of operational capacity; 33 Dths
LINEPACK RESTRICTIONS
Payback OFF the pipe will not be scheduled for all areas East of STA 325 on the 300 Line only. All payback in other areas will be evaluated at each cycle and scheduled only if operationally feasible.
STORAGE RESTRICTIONS
Tennessee will NOT approve any transfers from accounts at TGP Bear Creek Storage to SNG Bear Creek Storage (460017) (IS-PA, FS-PA) until further notice. Transfers into TGP Bear Creek Storage (460017) from SNG Bear Creek Storage will be allowed under the FS-PA storage service only with partner approvals.
**PLEASE NOTE THAT FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.
**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED SERVICE OUTAGES.
If you have any questions, please contact your Scheduler.