Notice Detail
           
Return To Results
TSP/TSP Name:  1939164-TENNESSEE GAS PIPELINE Critical: Y
Notice Type Desc (1):  PIPELINE CONDITIONS Notice Type Desc (2):  CURRENT PIPELINE CONDITIONS
Notice Eff Date/Time:  12/19/2022 7:20:00PM Notice End Date/Time:  12/20/2022 9:00:00am
Post Date/Time:  12/19/2022 7:20:00 PM Notice ID: 385347
Reqrd Rsp:  1 Rsp Date:  12/19/2022
Notice Stat Desc:  INITIATE Prior Notice: 
Subject:  RESTRICTIONS FOR 12-20-2022 EC
Notice Text:

Effective Evening Cycle (9:00) for the gas day of December 20, 2022 Tennessee restricted the following:

OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS

OFO DAILY CRITICAL DAY 1 FOR ALL AREAS EAST OF STA 325 ON THE 300 LINE ONLY FOR OVER-TAKES OUT OF THE SYSTEM OR UNDER-DELIVERIES INTO THE SYSTEM FOR ALL BALANCING PARTIES

RESTRICTIONS

·         Whistlep/TGP Whistler Receipt Nuece Receipt Meter (Pin 54847) - through approx 40% of SIPss increases  due to imbalance management quantity exceeded; 27,452 Dths

·         Net Mexi/TGP Gillrina Road Nueces Receipt Meter (Pin 47799) - through 100% of SOP increases  due to operational concerns; 9,987 Dths

·         Pine Pra/TGP Pine Prairie North Rap Delivery Meter (Pin 421043) - through approx 25% of SOP increases  due to operational concerns; 23,146 Dths

·         STA 834 (Segment 834 BH) - through approx 75% of SOP increases  due to nominations in excess of operational capacity; 55,124 Dths

·         Trnsco/TGP Heidelberg Missisippi Ja Delivery Meter (Pin 420291) - through 100% of SIPps increases  due to operational concerns; 10 Dths

·         TGP/SNG Rose Hill Miss Clarke Delivery Meter (Pin 420546) - through approx 81% of SIPps increases  due to nominations in excess of operational capacity; 75,813 Dths

·         Atmos Ky/TGP Lebanon Ky Marion Delivery Meter (Pin 420030) - through 100% of SIPss increases  due to nominations in excess of operational capacity; 767 Dths

·         Atmos Ky/TGP Harrodsburg Ky Boyle Delivery Meter (Pin 420028) - through 100% of SOP increases  due to nominations in excess of operational capacity; 1,546 Dths

·         MLV 314 East (Segment 314 BH) - through approx 82% of SOP increases  due to nominations in excess of operational capacity; 82,290 Dths

·         STA 315 (Segment 315 BH) - through approx 29% of SOP increases  due to nominations in excess of operational capacity; 40,304 Dths

·         STA 321 (Segment 321 FH) - through approx 94% of SOP increases  due to nominations in excess of operational capacity; 536,754 Dths

·         STA 325 (Segment 324 FH) - through 100% of SIPsp increases  due to force majeure between STA 325 to MLV 329; 125,779 Dths

·         MLV 336 East (Segment 336 FH) - through approx 27% of SOP increases  due to nominations in excess of operational capacity; 1,320 Dths

·         Z5HC North (Segment 299 FH) - through approx 99% of SOP increases  due to nominations in excess of operational capacity; 431,408 Dths

·         STA 245 (Segment 245 FH) - through 100% of SIPsp increases  due to scheduled maintenance and nominations in excess of operational capacity; 241,094 Dths

·         Wright Receipt Meter (Pin 412181) - through approx 91% of SIPss increases  due to nominations in excess of operational capacity; 130,809 Dths

·         MLV 256 East (Segment 256 FH) - through approx 82% of SOP increases  due to nominations in excess of operational capacity; 62,098 Dths

·         STA 261 Discharge East (Segment 261 FH) - through approx 8% of SOP increases  due to nominations in excess of operational capacity; 1,700 Dths

·         MLV 273 (Segment 284 FH) - through 100% of SOP increases  due to nominations in excess of operational capacity; 52,229 Dths

·         STA 268 North(Segment 268 FH) - through 100% of SOP increases  due to nominations in excess of operational capacity; 1,028 Dths

LINEPACK RESTRICTIONS

Payback OFF the pipe will not be scheduled for all areas East of STA 325 on the 300 Line only.  All payback in other areas will be evaluated at each cycle and scheduled only if operationally feasible.

STORAGE RESTRICTIONS

Tennessee will NOT approve any transfers from accounts at TGP Bear Creek Storage to SNG Bear Creek Storage (460017)(IS-PA, FS-PA) until further notice.  Transfers into TGP Bear Creek Storage (460017) from SNG Bear Creek Storage will be allowed under the FS-PA storage service only with partner approvals.

 

 

 

**PLEASE NOTE THAT FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.

**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED SERVICE OUTAGES.

If you have any questions, please contact your Scheduler.

 

....