Effective Intraday 2 Cycle (18:00) for the gas day of December 16, 2022 Tennessee restricted the following:
OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS
OFO DAILY CRITICAL DAY 1 FOR ALL AREAS EAST OF STA 325 ON THE 300 LINE ONLY FOR OVER-TAKES OUT OF THE SYSTEM OR UNDER-DELIVERIES INTO THE SYSTEM FOR ALL BALANCING PARTIES
RESTRICTIONS
· Gdr/TGP Rio Bravo Hidalgo Delivery Meter (Pin 421017) - through 100% of IT increases due to operational concerns; 20,000 Dths
· STA 409 - Donna Lateral (Segment 490 FH) - through approx 45% of SIPsp increases due to scheduled maintenance and nominations in excess of operational capacity; 4,261 Dths
· Pine Pra/TGP Pine Prairie North Rap Delivery Meter (Pin 421043) - through 100% of SOP increases due to operational concerns; 159,786 Dths
· Gulfsth/TGP Petal Storage Field For Delivery Meter (Pin 420797) - through 100% of SOP increases due to operational concerns; 200 Dths
· Trnsco/TGP Heidelberg Missisippi Ja Delivery Meter (Pin 420291) - through 100% of SIPps increases due to operational concerns; 10 Dths
· Hickoryr/TGP Mohawk Road Power Plt Delivery Meter (Pin 50789) - through 100% of PAYBACK TGP increases due to nominations in excess of operational capacity; 1,570 Dths
· MLV 314 East (Segment 314 BH) - through approx 97% of SOP increases due to nominations in excess of operational capacity; 106,569 Dths
· Debm/TGP Beirne Hill Sales Bradford Delivery Meter (Pin 48061) - through approx 70% of IT increases due to nominations in excess of operational capacity; 17,320 Dths
· STA 321 (Segment 321 FH) - through approx 81% of SOP increases due to nominations in excess of operational capacity; 231,391 Dths
· STA 325 (Segment 324 FH) - through approx 27% of PIP increases due to force majeure between STA 325 to MLV 329; 109,974 Dths
· Z5HC North (Segment 299 FH) - through approx 91% of SOP increases due to nominations in excess of operational capacity; 171,666 Dths
· STA 245 (Segment 245 FH) - through 100% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 206,693 Dths
· STA 261 Discharge East (Segment 261 FH) - through approx 91% of SOP increases due to nominations in excess of operational capacity; 54,806 Dths
· MLV 273 (Segment 284 FH) - through 100% of SOP increases due to nominations in excess of operational capacity; 54,528 Dths
LINEPACK RESTRICTIONS
Payback OFF the pipe will not be scheduled for all areas East of STA 325 on the 300 Line only. All payback in other areas will be evaluated at each cycle and scheduled only if operationally feasible.
STORAGE RESTRICTIONS
Tennessee will NOT approve any transfers from accounts at TGP Bear Creek Storage to SNG Bear Creek Storage (460017)(IS-PA, FS-PA) until further notice. Transfers into TGP Bear Creek Storage (460017) from SNG Bear Creek Storage will be allowed under the FS-PA storage service only with partner approvals.
**PLEASE NOTE THAT FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.
**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED SERVICE OUTAGES.
If you have any questions, please contact your Scheduler.