Effective Evening Cycle (9:00) for the gas day of December 16, 2022 Tennessee restricted the following:
OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS
OFO DAILY CRITICAL DAY 1 FOR ALL AREAS EAST OF STA 325 ON THE 300 LINE ONLY FOR OVER-TAKES OUT OF THE SYSTEM OR UNDER-DELIVERIES INTO THE SYSTEM FOR ALL BALANCING PARTIES
RESTRICTIONS
· Whistlep/TGP Whistler Receipt Nuece Receipt Meter (Pin 54847) - through approx 23% of PIP increases due to imbalance management; 5,661 Dths
· STA 40 South Of Carthage (Segment 132 FH) - through 100% of IT increases due to operational concerns; 16,300 Dths
· Pine Pra/TGP Pine Prairie North Rap Delivery Meter (Pin 421043) - through approx 74% of SOP increases due to operational concerns; 142,038 Dths
· STA 834 (Segment 834 BH) - through approx 30% of SOP increases due to nominations in excess of operational capacity; 10,440 Dths
· STA 860 (Segment 860 BH) - through 100% of SOP increases due to scheduled maintenance, nominations in excess of operational capacity and emergent repair at STA 860; 6,832 Dths
· Gulfsth/TGP Petal Storage Field For Delivery Meter (Pin 420797) - through 100% of SOP increases due to operational concerns; 200 Dths
· Trnsco/TGP Heidelberg Missisippi Ja Delivery Meter (Pin 420291) - through 100% of SIPps increases due to operational concerns; 10 Dths
· TGP/SNG Rose Hill Miss Clarke Delivery Meter (Pin 420546) - through approx 22% of SIPps increases due to nominations in excess of operational capacity; 19,175 Dths
· MLV 548 (Segment 542 BH) - through 100% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 66,783 Dths
· Hickoryr/TGP Mohawk Road Power Plt Delivery Meter (Pin 50789) - through 100% of PAYBACK TGP increases due to nominations in excess of operational capacity; 1,570 Dths
· MLV 314 East (Segment 314 BH) - through approx 83% of SOP increases due to nominations in excess of operational capacity; 114,668 Dths
· STA 321 (Segment 321 FH) - through approx 96% of SOP increases due to nominations in excess of operational capacity; 564,205 Dths
· STA 325 (Segment 324 FH) - through approx 98% of PIP increases due to force majeure between STA 325 to MLV 329; 156,430 Dths
· Z5HC North (Segment 299 FH) - through approx 99% of SOP increases due to nominations in excess of operational capacity; 265,427 Dths
· STA 245 (Segment 245 FH) - through 100% of SIPps increases due to scheduled maintenance and nominations in excess of operational capacity; 245,879 Dths
· Wright Receipt Meter (Pin 412181) - through approx 88% of SOP increases due to nominations in excess of operational capacity; 47,980 Dths
· MLV 256 East (Segment 256 FH) - through approx 51% of SOP increases due to nominations in excess of operational capacity; 36,618 Dths
· STA 261 Discharge East (Segment 261 FH) - through approx 81% of SOP increases due to nominations in excess of operational capacity; 56,297 Dths
· MLV 273 (Segment 284 FH) - through 100% of SOP increases due to nominations in excess of operational capacity; 54,528 Dths
· STA 268 North(Segment 268 FH) - through 100% of SOP increases due to nominations in excess of operational capacity; 2,660 Dths
LINEPACK RESTRICTIONS
Payback OFF the pipe will not be scheduled for all areas East of STA 325 on the 300 Line only. All payback in other areas will be evaluated at each cycle and scheduled only if operationally feasible.
STORAGE RESTRICTIONS
Tennessee will NOT approve any transfers from accounts at TGP Bear Creek Storage to SNG Bear Creek Storage (460017)(IS-PA, FS-PA) until further notice. Transfers into TGP Bear Creek Storage (460017) from SNG Bear Creek Storage will be allowed under the FS-PA storage service only with partner approvals.
**PLEASE NOTE THAT FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.
**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED SERVICE OUTAGES.
If you have any questions, please contact your Scheduler.