Effective Intraday 1 Cycle (14:00) for the gas day of December 14, 2022 Tennessee restricted the following:
OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS
OFO DAILY CRITICAL DAY 1 FOR ALL AREAS EAST OF STA 321 AND STA 245 FOR OVER-TAKES OUT OF THE SYSTEM OR UNDER-DELIVERIES INTO THE SYSTEM FOR ALL BALANCING PARTIES
RESTRICTIONS
· Whistlep/TGP Whistler Receipt Nuece Receipt Meter (Pin 54847) - through approx 87% of PIP increases due to imbalance management; 950 Dths
· MLV 707 East - Carthage Lateral (Segment 700 FH) - through 100% of SA increases due to nominations in excess of operational capacity; 13,765 Dths
· Pine Pra/TGP Pine Prairie North Rap Delivery Meter (Pin 421043) - through approx 75% of SOP increases due to operational concerns; 72,568 Dths
· STA 860 (Segment 860 BH) - through 100% of SOP increases due to scheduled maintenance and emergent repair at STA 860; 20,382 Dths
· Gulfsth/TGP Petal Storage Field For Delivery Meter (Pin 420797) - through approx 99% of SOP increases due to operational concerns; 10,912 Dths
· Trnsco/TGP Heidelberg Missisippi Ja Delivery Meter (Pin 420291) - through 100% of SIPps increases due to operational concerns; 10 Dths
· MLV 548 (Segment 542 BH) - through approx 62% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 32,451 Dths
· MLV 314 East (Segment 314 BH) - through 100% of SOP increases due to nominations in excess of operational capacity; 66,844 Dths
· Debm/TGP Beirne Hill Sales Bradford Delivery Meter (Pin 48061) - through approx 2% of SOP increases due to nominations in excess of operational capacity; 13,166 Dths
· STA 321 (Segment 321 FH) - through approx 73% of SOP increases due to nominations in excess of operational capacity; 296,776 Dths
· STA 325 (Segment 324 FH) - through approx 85% of PIP increases due to force majeure between STA 325 and MLV 329; 127,584 Dths
· Z5HC North (Segment 299 FH) - through approx 98% of SOP increases due to nominations in excess of operational capacity; 359,036 Dths
· STA 245 (Segment 245 FH) - through 100% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 231,693 Dths
· Wright Receipt Meter (Pin 412181) - through approx 81% of SIPss increases due to nominations in excess of operational capacity; 202,276 Dths
· MLV 256 East (Segment 256 FH) - through approx 84% of SOP increases due to nominations in excess of operational capacity; 128,776 Dths
· STA 261 Discharge East (Segment 261 FH) - through approx 51% of SOP increases due to nominations in excess of operational capacity; 14,391 Dths
· MLV 273 (Segment 284 FH) - through approx 85% of SOP increases due to nominations in excess of operational capacity; 31,642 Dths
LINEPACK RESTRICTIONS
Payback OFF the pipe will not be scheduled for all areas East of STA 321 and STA 245. All payback in other areas will be evaluated at each cycle and scheduled only if operationally feasible.
STORAGE RESTRICTIONS
Tennessee will not accept nominations for Interruptible Storage Injection Services under Rate Schedule IS (IS-MA) at the Northern MA (460018) storage field and Tennessee will not accept nominations for Interruptible Storage Injection Services under Rate Schedule IS (IS-PA) at the Bear Creek PA (460017) storage field.
Tennessee will NOT approve any transfers from accounts at TGP Bear Creek Storage to SNG Bear Creek Storage (460017)(IS-PA, FS-PA) until further notice. Transfers into TGP Bear Creek Storage (460017) from SNG Bear Creek Storage will be allowed under the FS-PA storage service only with partner approvals.
**PLEASE NOTE THAT FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.
**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED SERVICE OUTAGES.
If you have any questions, please contact your Scheduler.